Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP15-0060
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
03/12/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CBELL1 - |
03/12/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CBELL1 - |
01/10/2019 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - CREWS CONTINUE TO WORK ON THE BUILDINGS AND VERY LITTLE SITE WORK. SCHEDULE ANOTHER GRADING INSPECTION AT A LATER DATE TO DISCUSS THE BASIN ISSUES NOTED IN THE STORMWATER FOLLOWUP. |
06/21/2018 | ENGR Grading Final | DROBERTS | Continued | Entered by DROBERT5 - NO READY AT THIS TIME IT WILL NEED TO BE RESCHEDULED DURING THE TIME FRAME THAT THE FINAL INSPECTIONS ARE BEING DONE FOR PHASE 3. SITE VISIT ONLY. |
05/17/2018 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC ON SITE WENT OVER WORK TO COMPLET FOR PHASE #2. |
09/01/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
09/16/2016 | ENGR Grading Final | DROBERTS | Partial Approval | Entered by DROBERT5 - THE REVIEWERS ARE ACCEPTING THE MINOR FLOWS AND ARE BEING ASKED TO CLOSE THE CURRENT PERMITS. IF THIS IS DONE WE WILL NEED REVISED DRAWINGS AND A CERTIFICATION LETTER FROM THE ENGINEER OF RECORD. |
07/11/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PAVING WORK ON SOUTH SIDE OF SITE. |
10/13/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON RIP-RAP IN BASIN ON NORHT WEST SIDE OF SITE. |
03/12/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CBELL1 - |
04/17/2018 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PROVIDE AP COT PLANS FOR ALL CHANGES TO TRASH ENCLOUSRE. |
07/07/2015 | ENGR Grading Final | RLEDONNE | Partial Approval | Entered by RLEDONN1 - FOOTER PER NEW AP PLANS C5.8 HAS BEEN AP BY COT. |
06/08/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - PER RED LINE C5.8 FOR B5 CUM WALL #4 FOOTER INSTALLED PER RED LINE. PROVIDE COT AP C5.8 PAGE OF PLANS. |
04/29/2019 | ENGR Grading Final | BBENEDON | Approved | Entered by CBELL1 - |
08/29/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
08/15/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
08/10/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
08/01/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
06/19/2017 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
12/03/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
11/17/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY TODAY. |
10/22/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY. |
08/17/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC NO CONCERNS AT THIS TIME. |
08/05/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - GOT WITH GC ABOUT SWPPP CONTROLS.AND CONCRETE CLEAN UP. |
05/27/2015 | ENGR Grading Final | RLEDONN1 | Continued | Entered by RLEDONN1 - MET WITH GC ON SITE. |