Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP14-0235

Parcel: 99999999A

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP14-0235

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
05/27/2020 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 - Approved. Streets are public and therefore any sidewalk discrepancies are the jurisdiction of transportation and right of way
05/14/2020 ENGR Grading Final BBENEDON Correction Required Entered by RSALDAT1 - Correction required. West and north cul-de-sac, has three broken panels of sidewalk and the drainage structure portion of the accessible walkway is out of compliance at 2.8%slope.
03/27/2020 ENGR Grading Final BBENEDON Continued Entered by SFLORES2 - Stabilization has been added to some of the common areas however accessible sidewalks to require correction
02/05/2020 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - No change since last inspection. Sidewalks and common areas have been installed. Some sections of sidewalk are out of compliance.
01/08/2020 ENGR Grading Final BBENEDON Partial Approval Entered by DMERANZ1 - I met on site with Mark from DR Horton. The side appears to be roughly 25% complete. The sidewalks in front of the already constructed homes are good, however there’s a couple sections of sidewalk in the cul-de-sac near the entrance to the basin that require correction. Stabilization and access areas still required. Remove any construction debris prior. Correct erosion on basin walls. Complete all work and remove stormwater controls, and provide notice of termination of SWPPP permit for final approval.
11/21/2019 ENGR Grading Final BBENEDON Not ready for Inspection Entered by DMERANZ1 - Site closed due to rain
10/31/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Contractor is installing site perimeter wall. Drainage basins require stabilization.
08/22/2019 ENGR Grading Final BBENEDON Continued Entered by DMERANZ1 - Public street, sidewalks and Guard rails have been installed at drainage Crossings
04/23/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Unscheduled inspection, I did not speak with anyone from Borderland.Contractor is installing curbs and has started paving with the entrance off of Silverbell. The builder has completed one residential building at this time. Contractor has installed two concrete headers and is in the process of backfilling them at this time.
03/12/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - The site has been graded and the builder is constructing the first home on the site.
01/28/2019 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Contractors installing public utilities.
12/11/2018 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - 24 inch RCP at entrance okay. Continuation of 12 in HDPE overflow from site into Golf Course Contractor just starting to install electric utility lines
11/16/2018 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Jaime from Borderland at 603-0369. Installing public water system.
11/14/2018 ENGR Grading Final BBENEDON Continued Entered by BBENEDO1 - 30" RCP and 36" CMP as shown on Silverbell Crossing phase A DOT drawings, pg 3.
10/30/2018 ENGR Grading Final BBENEDON Continued Entered by CBELL1 - Three sections of 48 inch RCP installed at South drainage canal for unapproved revision from eec. Provide approved revisions. Schedule for inspections of headers. Alta engineering reviewed over excavation recompaction. Met with Jaime from Borderland, I showed him how to schedule an inspection through the ivr.
10/05/2018 ENGR Grading Final BBENEDON Continued Entered by CMURPHY1 - Met with Jaime on site 603-0369. Please post your site address. Please schedule inspections bi-weekly or as needed. Schedule inspections for all storm drain installations. Provide track out controls at both entrances and clean any track out onto the pavement. Contractor is installing grouted riprap on West Side, backfilling HCS connections on baby Bruno, installing HCS laterals along Dale's Crossing. Hand placed riprap along the west and south sides has already been completed. Concrete Bank protection has already been installed along the east side of site.
05/28/2020 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 -
05/28/2020 ENGR Grading Final BBENEDON Approved Entered by RSALDAT1 -
07/14/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
07/14/2020 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
04/23/2020 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - THIS SITE IS STILL UNDER CONSTRUCTION AT THIS TIME, THE INSPECTIONS WILL BE CALLED IN AND SCHEDULED BY THE CONTRACTOR ONCE THIS SITE IS COMPLETED
11/14/2018 ENGR Grading Final bbenedo1 Continued Entered by BBENEDO1 - Contractor installing public water service. Borderland working in east drainage conal fron DOT plans