Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/14/2016 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/20/2015 |
PDSD Engineering Division Pre-Construction SITE |
DROBERTS |
Continued |
Entered by DROBERT5 - MET WITH CONCORD GENERAL CONTRACTING AND WALKED THE SITE TOO SEE WHAT HAS BEEN HAPPENING OVER THE PAST MONTH. THE CREWS ARE INSTALLING A NEW INTERCEPTOR SO THAT THEY CAN REMOVE THE EXISTING SYSTEM. THEY HAVE COMPLETED THE INSTALLATION AND ARE CURRENTLY WORKING ON THE PLACEMENT OF BACKFILL. I WILL ADVISE MIKE TO STOP BY THE SITE AND SEE WHERE THEY ARE AT ON MONDAY. |