Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 11/08/2016 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by MRUSSO1 - |
| 11/08/2016 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by MRUSSO1 - |
| 04/22/2016 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - THE CONTRACTOR IS WORKING ON THE CONSTRUCTION OF THE BUILDING BETWEEN THE 4' TO 8' LEVELS AT THIS TIME. NO INSPECTIONS HAVE BEEN SCHEDULED FOR THIS DEVELOPMENT PACKAGE FOR THIS SITE. A MESSAGE HAS BEEN LEFT WITH THE OFFICE OF CORNELL CONSTRUCTION 742-7227 AND THE Y HAVE BEEN ADVISED TO CALL IN THE ENGINEERING PRE CONSTRUCTION. |
| 10/08/2015 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - NO WORK AT THIS TIME. |
| 11/08/2016 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by MRUSSO1 - |
| 07/11/2016 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by MRUSSO1 - PRE-GROUT INSPECTION FOR TRASH ENCLOSURE - OK FOR CONCRETE |
| 06/22/2016 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by MRUSSO1 - RE-BAR LAY OUT INSTALLED PER APPROVED PLANS |
| 11/08/2016 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by MRUSSO1 - |
| 08/03/2016 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by MRUSSO1 - 1) LOOKED AT PEDESTRIAN ACCESS TO THE BLDG AND SIDEWALK SLOPES ALONG ALL THREE ROADS
2) NEED RAILING ON TWO OF THE SIDEWALK RAMPS FROM THE EAST ACCESS AND SOUTH ACCESS.
3) ENSURE STORM WATER ALONG THE NORTH SIDE OF THE BLDG DRAINS PER APPROVED PLANS
4) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME. |
| 06/07/2016 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by MRUSSO1 - NO SIGNIFICANT SITE WORK AT THIS TIME, CONTRACTOR WORKING ON THE BLDG |