Inspection History Details
Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP14-0202
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/21/2017 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
09/26/2017 | ENGR Engineering Final | DROBERTS | Not ready for Inspection | Entered by DROBERT5 - NO SITE CHANGES HAVE BEEN MADE AT THIS TIME FROM THE PREVIOUS INSPECTIONS DATED 10/10/16. COMPLETE THE SITE AS SHOWN ON THE APPROVED PLANS (CHECK DAMS) OR PROVIDE APPROVED REVISED DRAWINGS SHOWING THAT THESE HAVE BEEN ELIMINATED FORM THIS SITE PLAN. I WALKED THE SITE WITH VINNIE FROM A & E AND LOOKED AT THE CORRECTIONS THAT WE ARE ASKING FOR. HE WILL CONTACTG THE NECESSARY PARTIES (CONTRACTOR) ANS SEE IF THEY CAN COMPLETE THE WORK AS REQUESTED. |
09/18/2017 | ENGR Engineering Final | DROBERTS | Not ready for Inspection | Entered by DROBERT5 - NOTHING HAS HAPPENED WITH THIS SITE TO THIS DATE |
09/01/2017 | ENGR Engineering Final | DROBERTS | Not ready for Inspection | Entered by DROBERT5 - THIS SITE WILL BE SCHEDULED NEXT WEEK IF THE INFORMATION THAT HAS BEEN REQUESTED IS MADE AVAILABLE FOR THE INSPECTION. |
08/22/2017 | ENGR Engineering Final | DROBERTS | Not ready for Inspection | Entered by DROBERT5 - THIS SITE HAS NOT BEEN APPROVED DUE TO THE CHANGES THAT HAVE BEEN MADE TO THE DEVELOPMENT PACKAGE. REVISED DRAWINGS FOR ALL CHANGES THAT HAVE BEEN MADE TO THE SITE ARE REQUIRED ALONG WITH THE CERTIFICATION LETTER FROM THE ENGINEER OF RECORD FOR THE SITE. |
10/10/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALL CHECK DAM PER DETAILS AND FILTER FABRIC AND DIMENSIONS COMPLET WORK ON PAGE C1.0 MARKED IN RED. |
10/07/2016 | ENGR Engineering Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - |
07/19/2016 | ENGR Engineering Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - SWPPP INSPECTIONS DONE BY TRANSPOTATION ENVIRONMENTAL INSPECTION. PROVIDE ENGINEER OF RECORD AS-BUILTS AP BY COT FOR ALL GRADING AND DRAINAGE CHANGES. POVIDE. CATCH BASINS CERT LETTER FROM ENGINEER OF RECORD FOR ALL GRADING AND DRAINAGE AND STORM WATER PIPING. DEEPS OF RIP-RAP COMPLET MITIGATION AREAON EAST SIDE OF SITE PER AP PLANS. |
07/15/2016 | ENGR Engineering Final | RLEDONNE | Denied | Entered by RLEDONN1 - PROVIDE INSPECTION HISTORY. PROVIDE AP COT PLANS AND PERMITS. |