Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/21/2015 |
PDSD Engineering Division Pre-Construction SITE |
RLEDONNE |
Approved |
Entered by RLEDONN1 - |
| 10/07/2015 |
PDSD Engineering Division Pre-Construction SITE |
RLEDONNE |
Not ready for Inspection |
Entered by RLEDONN1 - NO PLANS OR PREMITS ON SITE. |
| 10/02/2015 |
PDSD Engineering Division Pre-Construction SITE |
DROBERTS |
Not ready for Inspection |
Entered by DROBERT5 - CONTRACTOR WORKING ON SITE, THEY WILL BE SCHEDULING A PRE-CON MEETING FOR THE FIRST PART OF NEXT WEEK. TRACKOUT ROCK IS IN PLACE AT THIS TIME BUT WADDLE HAS NOT BEEN PLACED IN THE LOW LYING AREAS. |
| 10/06/2015 |
PDSD Engineering Division Pre-Construction SITE |
RLEDONNE |
Not ready for Inspection |
Entered by RLEDONN1 - PROVIDE AP PLANS AND NOI FOR PRE-CON MEETING. DROPED OFF PRE-CON PACKET. |