Permit: DP14-0189

Parcel: 14026038A

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP14-0189

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
01/06/2016 ENGR Grading Final ROBERTS Approved Entered by DROBERT5 -
02/12/2016 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
01/06/2016 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 -
01/12/2016 ENGR Grading Final ROBERTS Correction Required Entered by DROBERT5 - CHECK ON THE INSTALLATION OF RAIL ADJACENT TO THE BASIN AREA WHERE IT HAS BEEN ELIMINATED. SOME OF THE AREAS HAVE SLOPES STEEPER THAN 1:4 AND ARE DEEPER THAN 2 FEET. PER THE PIMA COUNTY AND CITY OF TUCSON RETENTION/DETENTION BASIN MANUEL THESE AREAS REQUIRE HANDRAIL.
12/30/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - RAMP ON WEST SIDE OF PARKING AREA OVER 8.3% . COMPLET ALL WORK ON AP PLANS. PROVIDE CERT LETTER AND AS-BUILTS.
12/23/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING IN RIGHT OF WAY.
12/16/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WALKED SITE MET WITH GRADING CONTRACTOR.
11/25/2015 ENGR Grading Final LEDONNE Not ready for Inspection Entered by RLEDONN1 -
11/23/2015 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - CONTRACTOR ASKED ABOUT THE CONSTRUCTING OF HANDRAIL ALONG BOTHE SIDES OF THE SIDEWALK BETWEEN THE BASIN AND THE PARKING. I HAVE ADVISED THEM THAT THE CURRENT CODE REQUIREMENTS SAYS THAT HANDRAIL IS REQUIRED IN AREAS WHERE 30 INCHES OF DROPOFF HAS OCCURED IN AN AREA ADJACENT TO A PEDESTRIAN ACCESS AREA.
10/26/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 -
10/22/2015 ENGR Grading Final RLEDONNE Not ready for Inspection Entered by RLEDONN1 - NO ACTIVITY ON SITE.
02/12/2016 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
01/06/2016 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - CREWS STILL WORKING THROUGHOUT THE SITE
12/24/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - STARTED WALKING SITE WITH AP PLANS.
11/23/2015 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - CREWS WORKING ON THWE PLACEMENT OF THE ASPHALT FOR THE PARKING LOTS WEST OF THE NEW STORE, CREWS WILL CONTINUE THIS PLACEMENT INTO THE WEEKEND.
10/30/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
10/26/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON CURB ON EAST SIDE OF BUIDING.
09/18/2015 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - NPL IS PULLING LINE ALONG THE EAST BOUNDARY CREWS CONTINUE TO BUILD FORMS FOR THE FUTURE CATCHBASINS. CREW PLACING SHADING MATERIAL IN THE AREA OF THE TANK FARM.
09/16/2015 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - CREWS EXCAVATING IN THE SOUTH EAST QUADRANT OF THE SITE, BUILDING FORMS FOR THE FUTURE CATCH BASINS ON THIS SITE, CREWS WORKING IN THE FUEL TANK AREA.
09/17/2015 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - CREWS WORKING ON POURING THE BOLLARDS AND SOME FOOTINGS ON THE WEST SIDE OF THE BUILDING AT THE FRONT ENTRANCE. CREWS ALSO WORKING ON MANHOLE PLACEMENT THROUGHOUT THE SITE, PREPPING AND FOR CATCH BASIN POURS NEXT WEEK, WORKING IN THE TANK AREA AT THE SOUTHWEST CORNER OF THS SITE.
09/10/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PER HIGH LIGHTS ON 37 OF 51 INSTALL MANHOLE PER DETAIL ON AP PLANS.
09/10/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PER HIGH LIGHTS ON PAGE 37 OF 51
09/09/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PER HIGH LIGHTS ON 35 OF 51.
09/04/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PER HIGH LIGHTS ON 35OF 51.
09/03/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - HIGH LIGHTS ON 35 OF 51 FOR STORM DRAIN PIPING.
09/02/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS ON PAGE 34 0F 51 AND 34 OF 51.
09/01/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PER HIGH LIGHTS
08/31/2015 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS FOR STORM DRIAN PIPING ON PAGE 34 OF 51.
02/12/2016 ENGR Grading Final DROBERTS Approved Entered by DROBERT5 -
01/06/2016 ENGR Grading Final DROBERTS Not ready for Inspection Entered by DROBERT5 - HANDRAIL IS NEEDED IN THE AREA OF THE RETENTION BASIN SOUTH OF THE FUEL ISLANDS. THIS NEW RAILING SHOULD BE REFLECTED IN THE AS-BUILT DRAWINGS FOR THS SITE.