Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/02/2021 |
ENGR Engineering Final
|
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 01/11/2021 |
ENGR Engineering Final
|
MHERNANDEZ |
Not ready for Inspection |
Entered by VLEON1 - SIDEWALK AND DRIVEWAY NEED IN FIVE LOTS
|
| 09/11/2020 |
ENGR Engineering Final
|
DROBERTS |
Not ready for Inspection |
Entered by JSCHNEI2 - NOT READY AT THIS TIME, MISSING THE SIDE WALK AND DRIVEWAYS, DG AND LANDSCAPING FOR LOTS #5, #9 & 10, 12 - 16. THE SIDEWALKS WILL BE CHECKED FOR ADA COMPLIANCE OF SLOPES PRIOR TO FINAL APPROVAL. |