Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/27/2015 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - 1) INSTALL SEDIMENT CONTROLS PER YOUR STORM WATER PLAN AND RECOMMENDATIONS MADE DURING INSPECTION -WEST PERIMETER/NORTHSIDE AND NORTH SECTION EAST SIDE.
2) INSTALL A STABILIZED CONSTRUCTION ENTRANCE.
3) POST A COPY OF YOUR NOI AND/OR AZPDES#
4) INSTALL A CONCRETE WASH OUT WHEN APPLICABLE
5) PERFORM STORM WATER SELF INSPECTIONS PER YOUR SWPPP
6) CALL FOR RE-INSP WHEN SEDIMENT CONTROLS HAVE BEEN INSTALLED
7) SWEEP UP TRACKING AS NEEDED |