Inspection History: SITE - Stormwater Follow-up
Permit Number - DP14-0127
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
04/10/2015 | SITE - Stormwater Follow-up | MRUSSO | Approved | Entered by DROBERT5 - |
03/12/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by CSHARRA1 - 1. ENSURE SEDIMENT CONTROLS REMAIN IN PLACE UNTIL THE SITE IS 100% STABILIZED 2. FILE A NOTICE OF TERMINATION (NOT) WITH THE ARIZONA DEPARTMENT OF ENVIRONMENTAL QUALITY (ADEQ) WHEN SITE/GRADING IS COMPLETE |
03/06/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
03/04/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
02/24/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME |
02/18/2015 | SITE - Stormwater Follow-up | MRUSSO | Approved | Entered by DROBERT5 - SOME CURBING HAS BEEN INSTALLED, SOME SEDIMENT CONTROLS HAVE BEEN REMOVED. PAVING NEXT WEEK |
02/12/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR SWPPP. 3) SWEEP UP TRACKED SOIL AS NEEDED |
02/11/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) NO SITE/GRADING CHANGES AND/OR CONCERNS AT THIS TIME |
02/04/2015 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) NO STORM WATER CONCERNS AT THIS TIME. 2) SOME CHANGES TO PROJECT DUE TO THE FACT THAT THE CONTRACTOR RAN INTO UNKNOWN MATERIAL ON SITE |