Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 04/10/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/12/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by CSHARRA1 - 1. ENSURE SEDIMENT CONTROLS REMAIN IN PLACE UNTIL THE SITE IS 100% STABILIZED
2. FILE A NOTICE OF TERMINATION (NOT) WITH THE ARIZONA DEPARTMENT OF ENVIRONMENTAL QUALITY (ADEQ) WHEN SITE/GRADING IS COMPLETE |
| 03/06/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 03/04/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 02/24/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME |
| 02/18/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Approved |
Entered by DROBERT5 - SOME CURBING HAS BEEN INSTALLED, SOME SEDIMENT CONTROLS HAVE BEEN REMOVED.
PAVING NEXT WEEK |
| 02/12/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED PER YOUR SWPPP.
3) SWEEP UP TRACKED SOIL AS NEEDED |
| 02/11/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
2) NO SITE/GRADING CHANGES AND/OR CONCERNS AT THIS TIME |
| 02/04/2015 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) NO STORM WATER CONCERNS AT THIS TIME.
2) SOME CHANGES TO PROJECT DUE TO THE FACT THAT THE CONTRACTOR RAN INTO UNKNOWN MATERIAL ON SITE |