Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP14-0086
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/13/2017 | ENGR Grading Final | MRUSSO | Approved | Entered by DROBERT5 - |
02/13/2017 | ENGR Grading Final | MRUSSO | Approved | Entered by DROBERT5 - |
02/13/2017 | ENGR Grading Final | MRUSSO | Approved | Entered by DROBERT5 - |
10/07/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME |
06/23/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT CHANGES AN/OR CONCERNS AT THIS TIME |
05/29/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - PRIOR TO FINAL 1) PROVIDE AN AS-BUILT DRAWING FOR INSPECTION 2) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD 3) COMPLETE PHASE I CONSTRUCTION PER APPROVED PLANS 4) CLEAN OUT NEW AND EXISTING CATCH BASINS 5) FILE A (NOT) WITH ADEQ |
04/16/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO SITE/GRADING CHANGES OR CONCERNS AT THIS TIME |
04/14/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - 1) ADDRESS TRASH ENCLOSURE ISSUE WITH THE CITY OF TUCSON ZONING SECTION 2) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD AT FINAL 3) PROVIDE AN AS-BUILT AT FINAL INSPECTION |
03/09/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME |
03/02/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO CHANGES AT THIS TIME |
02/24/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME |
02/06/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - 1) PRIOR TO APPROVAL CLEAN OUT ALL STORM WATER CATCH BASIN 2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENGINEER OF RECORD 3) CLEAN OUT RET/DET BASIN - RE-SCARIFY 4) SWEEP UP EAST/SE PARKING AREA 5) COMPLETE SITE WORK PRIOR TO BLDG OCCUPANCY 6) PERFORM STORM WATER SELF INSPECTIONS - MAINTAIN SEDIMENT CONTROLS UNTIL SITE IS STABILIZED |
01/06/2015 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - TOOK PICTURES OF INSTALL OF CATCH BASINS SHOWN ON APPROVED PLAN - PRE-FAB BASINS AND CONTRACTOR GROUTED PIPE INTO ECH SIDE. MATERIAL AND SIZE OK |
12/23/2014 | ENGR Grading Final | MRUSSO | Continued | Entered by DROBERT5 - 1) CONTRACTOR INSTALLING 12" CMP ALONG EAST SIDE OF NEW BLDG. 2) ENSURE TO BED PIPE TO SPRING LINE 3) CALL FOR INSPECTION PRIOR TO COVERING AND POURING NEW CATCH BASINS 4) OK TO COVER SECTION OF PIPE 5) CALL FOR INSPECTION PRIOR TO POURING CATCH BASINS. |