Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/15/2015 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - 1) PROJECT IS GREATER THAN 1 ACRE AND IS UNDER A STORM WATER PERMIT.
2) CONTRACTOR HAS FILED A NOTICE OF INTENT WITH ADEQ
3) INSTALL SEDIMENT CONTROLS PER YOU APPROVED STORM WATER PLAN AND PER MY INSPECTION.
4) CALL FOR RE-INSPECTION WHEN CONTROLS HAVE BEEN INSTALLED.
5) ENSURE STORM WATER SELF INSPECTION ARE PERFORMED AND DOCUMENTED.
6) INSTALL A STABILIZED CONSTRUCTION ENTRANCE AND CONCRETE WASH OUT PER YOU PLAN.
7) WILL VERIFY NPPO |