Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 01/16/2015 |
ENGR Grading Final |
RLEDONN1 |
Approved |
Entered by RLEDONN1 - TRASH ENCLOSURE REBAR INSTALL PER PLANS. |
| 04/21/2015 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by ARUIZ1 - |
| 03/11/2015 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - WALKED SITE WITH. |
| 06/04/2015 |
ENGR Grading Final |
RLEDONNE |
Approved |
Entered by RLEDONN1 - |
| 02/23/2015 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO GRADING ACTIVITY. |
| 01/12/2015 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME. |
| 12/31/2014 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - WORKING ON BUILDING WALL.NO GRADING ACTIVITY. |
| 12/22/2014 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO GRADING ACTIVITY. |
| 11/19/2014 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO CONCERNS AT THIS TIME. |
| 10/28/2014 |
ENGR Grading Final |
RLEDONN1 |
Continued |
Entered by RLEDONN1 - CONCRETE AND TRACK OUT HAVE BEEN CLEANED UP. |
| 10/15/2014 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - STARTED GRADING WORK. |
| 10/10/2014 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
| 10/07/2014 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by RLEDONN1 - MET WITH GC FOR PRE-CON. |
| 10/18/2022 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 04/21/2015 |
ENGR Grading Final |
RLEDONNE |
Continued |
Entered by ARUIZ1 - |
| 09/23/2014 |
ENGR Grading Final |
DROBERTS |
Continued |
Entered by DROBERT5 - MINOR CONFLICTS WITH THE SWG PIPE LINE MAY NEED TO BE DISCUSSED WITH THE ENGINEER OF RECORD FOR THIS SITE. CURRENTLY THE CONTRACTOR IS WORKING ON THE GASLINE ON THE SOUTHSIDE OF THE SITE AT THIS TIME. |