Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 06/05/2017 |
ENGR Engineering Final
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/01/2017 |
ENGR Engineering Final
|
DROBERTS |
Partial Approval |
Entered by DROBERT5 - OK FOR THE TEMPORARY C OF O AT THIS TIME. FINAL WILL NOT BE GIVEN TILL THE FOLLOWING ITEMS HAVE BEEN COMPLETED AND REINSPECTED. 1) INSTALL ALL THE GATES AS SHOWN ON THE APPROVED PLANS. 2) REDIRECT THE ROOF DRAINAGE OFF OF THE SIDEWALK AT THE SOUTHEAST CORNER OF THE NEW BUILDING SO THAT IT DOES NOT AFFECT THE PEDESTRIAN ACCESS INTO THE BUILDING. 3) CORRECT THE TRIP HAZARD IN THE SIDEWALK AREA LOCATED AT THE SOUTHWEST CORNER OF THE NEW BUILDING. THIS WILL REQUIRE THE REMOVAL OF SOME OF THE EXISTING SIDEWALK AND REPOURING IT SO THAT IT ALLOWS ACCESS ALONG THE SOUTHSIDE OF THE NEW BUILDING. |
| 05/16/2017 |
ENGR Engineering Final
|
DROBERT5 |
Continued |
Entered by DROBERT5 - SEE PREVIOUS NOTES |
| 05/04/2017 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - AWAITING APPROVAL FOR LANDSCAPING CHANGES |
| 05/02/2017 |
ENGR Engineering Final
|
MRUSSO |
Partial Approval |
Entered by DROBERT5 - 1) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD ADDRESSING CHANGES MADE TO THE SITE
2) COMPLETE LANDSCAPING. |
| 04/10/2017 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - WALKED THE SITE WITH THE ENGINEER OF RECORD. DISCUSSED COMPLETION OF PERMIT REQUIREMENTS |
| 03/30/2017 |
ENGR Engineering Final
|
MRUSSO |
Prior to Final Inspectn |
Entered by DROBERT5 - 1) ADDRESS PEDESTRIAN ACCESS EAST SIDE OF BLDG #1 NEAR COLUMBUS ROAD. SIDEWALK WILL NOT MATCH APPROVED PLANS, HOWEVER IT WILL BE ADA COMPLIANT.
2) PEDESTRIAN ACCESS SIDEWALK ALONG THE NE CORNER OF BLDG #2 WILL BE CHANGED, ENSURE ACCESS MEETS ADA.
3) ENSURE ALL BIKE PARKING REQUIREMENTS ARE MET UNLESS THE APPROVED PLANS ARE REVISED
4) AT REAR OF BLDG #2 THERE ARE TWO SIDEWALKS THAT PROVIDE ACCESS TO BLDG. ONE MEETS ADA AND ONE DOESN'T. ENSURE SIDEWALKS ARE LABLED AS SUCH OR MODIFY ACCESS SO BOTH SIDEWALKS MEET ADA |