Inspection Status: Passed
Inspection History: ENGR Engineering Final
Permit Number - DP13-0200
Inspection Description - ENGR Engineering Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
09/12/2016 | ENGR Engineering Final | DROBERTS | Approved | Entered by DROBERT5 - |
09/01/2016 | ENGR Engineering Final | DROBERTS | Denied | Entered by DROBERT5 - MET WITH THE CONTRACTOR AND LOOKED OVER THE WORK THAT THEY HAVE BEEN DOING ON THE SITE RECENTLY. THEY HAVE ADVISED ME THAT THEY ARE PLANNING ON INSTALLING THE WIER OUTLET FOR THE BASIN. I HAVE ADVISED THEM THAT THE WIER WALL THAT ARE PREPARING TO COMPLETE IS TOO LONG AND STICKS OUT INTO THE RIGHT-OF-WAY AND THAT THEY WOULD NEED A PERMIT FROM THE TRANSPORTATION DEPARTMENT. I HAVE ASKED THAT THEY CONTACT THE TRANSPORTATION FOR THIS AREA AND HAVE HIM LOOK OVER WHAT THEY WANT TO DO BEFORE THEY GO ANY FURTHER. HE WILL CHECK INTO THIS THIS NEXT WEEK AND WILL RESCHEDULE THE SITE INSPECTION ACCORDINGLY. |
08/24/2016 | ENGR Engineering Final | RLEDONNE | Not ready for Inspection | Entered by RLEDONN1 - MET WITH GC ON SITE CHECKING ON SLOPES FOR SIDEWALKS FORMS ONLY. ONE SPOT OVER 2% CROSS SLOPE AND ONE SPOT OVER 5% RUNNING SLOPES. |
08/08/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH GC AND WALKED SITE. |
08/05/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - WALKED SITE WITH DAVE . |
07/22/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO CHANGES FROM LAST INSPECTION. |
05/24/2016 | ENGR Engineering Final | RLEDONNE | Not ready for Inspection | Entered by DROBERT5 - CROSS SLOPE ON NEW SIDE WALKS WEST SIDE OF BUILDING OVER 2%. |
05/24/2016 | ENGR Engineering Final | RLEDONNE | Not ready for Inspection | Entered by DROBERT5 - |
05/11/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON ADA RAMP. |
02/10/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - INSTALLING ROCK IN BASIN ON NORTH SIDE OF SITE. |
02/02/2016 | ENGR Engineering Final | RLEDONNE | Continued | Entered by RLEDONN1 - DAVE ROBERTS AND I WALKED SITE WITH GC REPS . ARCHITET AND CHURCH REPS . WENT OVER THE WORK THAT NEEEDS TO BE DONE FOR FINAL. |