Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 01/09/2014 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - 1) MET WITH SUPERINTENDENT
2) SCOPE OF WORK HAS CHANGED, ENTIRE SITE HAS BEEN DEMOLISHED AND WILL BE PAVED.
3) AN APPROVED REVISION SHOWING CHANGES MUST BE AVAILABLE FOR INSPECTION
4) CONTRACTOR HAS A ROW PERMIT FOR WORK IN THE RIGHT OF WAY
5) SITE IS LESS THAN 1 AC NO SWPP REQUIRED
6) KEEP DISTURBED SOIL ON SITE DURING CONSTRUCTION
7) INSTALL SEDIMENT CONTROLS IN FRONT OF STORM DRAIN CULVERT IN ROW |
| 12/27/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Continued |
Entered by DROBERT5 - NO CONSTRUCTION ACTIVITY ON SITE |
| 12/12/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Continued |
Entered by DROBERT5 - NO CONSTRUCTION ACTIVITY AT THIS TIME |
| 11/06/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Continued |
Entered by DROBERT5 - NO ACTIVITY |
| 10/31/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Continued |
Entered by DROBERT5 - NO ACTIVITY, NO CONSTRUCTION |
| 10/23/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Continued |