Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP13-0163

Parcel: 13014447A


Addresses:

1305 S ALVERNON WY


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP13-0163

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
06/26/2019 ENGR Grading Final RLEDONNE Approved Entered by RLEDONN1 -
08/19/2014 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
08/19/2014 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
08/19/2014 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
07/18/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) SIDEWALK ALONG WEST/NW SIDE PER APPROVED PLANS - OK TO POUR 2) ENSURE SEDIMENT CONTROLS ARE RE-ESTABLISHED ALONG THE SOUTH/SW SIDE OF SITE TO PROTECT EXISTING REGULATED WASH 3) PROTECT ALL CATCH BASINS AND BUBBLER FROM CONSTRUCTION 4) MAKE SURE ALL CLEAN OUTS/MANHOLES ARE PROTECTED FROM PAVING
07/15/2014 ENGR Grading Final MRUSSO Correction Required Entered by DROBERT5 - 1) REMOVE SILT FENCE ALONG EAST PERIMETER 2) RE-ESTABLISH SILT FENCE ALONG THE SOUTH/SOUTHWEST CORNER WHERE THE STORM WATER DROPS INTO THE WASH 3) SWEEP UP SOIL ALONG THE WEST SIDE ADJACENT ROADWAY AND SOME ALONG THE NORTH SIDE 4) POTECT STORM DRAIN INLETS AND BUBBLER BOX FROM SILT FROM CONSTRUCTION. 5) SIDE WALK ALONG WEST SIDE OF BLDG, FORMS OK 6) CUT BACK OUTLET STORM PIPE TO MATCH DRAINAGE WAY SLOPE.
07/10/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SITE CHANGES AND/OR COCNERNS
04/25/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) MAINTAIN SEDIMENT CONTROLS THROUGHOUT CONSTRUCTION. CONTROLS MUST STAY IN PLACE UNTIL THE SITE IS STABILIZED. 2) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED 3) RE-INSTALL SEDIEMNT CONTROLS ALONG THE WEST AND SOUTH SIDE OF SITE 4) CONTRACTOR WORKING ON BUILDING, MINIMAL SITE WORK AT THIS TIME
04/02/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) INSTALL/RE-INSTALL SEDIMENT CONTROLS ALONG THE NW CORNER OF THE SITE AND IN ANY LOCATION CONTROLS WERE TEMP REMOVED FOR CONSTRUCTION. 2) ANY SPOILS FROM WORK IN THE EXISTING DRAINAGE WAY/WASH NEED TO BE BROUGHT BACK ON TO SITE 3) SITE IS STILL UNDER A STORM WATER PERMIT UNTIL CONSTRUCTION IS COMPLETED - CONTROLS MUST REMAIN IN PLACE UNTIL THE SITE IS STABILIZED. 4) INSPECTED BANK REPAIR WORK ALONG EXISTING DRAINAGE - OK TO POUR CONCRETE
02/27/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT SITE CHANGES AT THIS TIME
02/19/2014 ENGR Grading Final MRUSSO Correction Required Entered by DROBERT5 - 1) INSPECTED STORM SYSTEM ALONG THE EAST SIDE OF THE BLDG, TOOK PICS. 2) ENSURE STORM SYSTEM PIPE IS GRADED PER APPROVED PLAN.
02/13/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - CONTRACTOR INSTALLING STORM PIPE ALONG THE EAST SIDE OF THE BLDG. TOOK PICTURES OF STORM PIPE TIE-IN TO EXISTING DRAINAGE CHANNEL
02/12/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - TOOK A LOOK AT INSTALL OF STORM PIPE ALONG THE WEST AND SOUTH SIDES - INSTALL PER PLAN
02/11/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) INSPECTED STORM PIPE INSTALL ALONG WEST AND SOUTH SIDES OF SITE 2) TOOK PICTURES OF TRUNK LINE, LATERAL ROOF DRAIN CONNECTIONS, CATCH BASIN, AND MANHOLES. 3) STORM SYSTEM WAS INSTALLED PER APPROVED PLAN. 4) ENSURE A CONCRETE/MATERIALS WASH OUT IS ON SITE AND IS USED. 5) ENSURE STORM WATER SEDIEMNT CONTROLS ARE MAINTAINED THROUGHOUT THE CONSTRUCTION
02/10/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - CONTRACTOR INSTALLING UNDERGROUND STORM DRAIN LINE. PICTURES TAKEN STORM PIPE INSTALLED PER APPROVED PLAN. WILL RE-INSPECT ON MONDAY 2/10
02/06/2014 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR COMPLETED INSTALLATION OF STORM WATER CONTROLS PER PLAN 2) ENSURE CONTROLS ARE MAINTAINED THROUGHOUT CONSTR 3) CONTRACTOR STARTED WORK ON INSTALL OF STORM WATER DRAINAGE PIPE - PICS TAKEN 4) NO SIGNIFICANT STORM WATER COCERNS AT THIS TIME