Inspection Status: Passed
Inspection History: ENGR Grading Final
Permit Number - DP13-0151
Inspection Description - ENGR Grading Final
Inspection Status - Passed
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
10/31/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
10/31/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
01/13/2014 | ENGR Grading Final | ELEIBOL1 | Prior to Final Inspectn | Entered by GBONILL1 - TIER 1 REVISION: Elevating approx 8 -in on eastern lots while compaction for 3 lots is underway. Spoke with Architect Scott Neeley RA 343-8153, 13JAN14. East swale will be provided at east side of east lot, within property limits. Any additional erosion protection in the form of riprap or gravel may be neeeded as determined by EOR and Inspector in the field. |
10/31/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
02/23/2016 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO CHANGES TO SITE FROM LAST INSPECTION. |
08/18/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY ON SITE. |
07/23/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME. |
04/09/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by ARUIZ1 - NO GRADING ACTIVITY |
03/03/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - GOT WITH GC ABOUT PROVIDING AP PLANS FOR ALL CHANGES TO AP PLANS. |
01/08/2015 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY. |
12/18/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
12/02/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE AT THIS TIME. |
11/12/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY. |
10/21/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY . |
10/13/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
09/02/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - GATE LOCKED NO ACTIVITY. |
08/14/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY. |
08/07/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - |
07/21/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME. |
07/17/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY. |
06/13/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE . |
06/05/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY ON SITE. |
05/14/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY. |
04/30/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
04/25/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - |
04/08/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE AT THIS TIME. |
04/03/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY. |
03/14/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY AT THIS TIME. |
03/11/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO GRADING ACTIVITY . WORKING ON BUILDING PAD. |
03/04/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME. |
01/24/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - OVER XING THE NORTH SIDE OF SITE. |
01/07/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITYONSITE ATTHIS TIME. |
01/07/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE AT THIS TIME. |
10/31/2017 | ENGR Grading Final | RLEDONNE | Approved | Entered by RLEDONN1 - |
02/24/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |
02/11/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - I HAVE RECEIVED LETTER FROM PATTISON EVANOFF. STILL NEED CERT LETTER FOR ALL GRADING AND DRAINAGE FROM ENGINEER. |
02/07/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - MET WITH ENGINEEN ON SITE ABOUT ACCESSABLE PARKING. |
02/04/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - WORKING ON BUILDING PADS. |
02/03/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY AT THIS TIME. |
01/29/2014 | ENGR Grading Final | RLEDONNE | Continued | Entered by RLEDONN1 - NO ACTIVITY ON SITE. |