Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 07/21/2014 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 06/30/2014 |
ENGR Grading Final |
MRUSSO |
Partial Approval |
Entered by DROBERT5 - COMPLETE PAVING AND ALL SITE/LANDSCAPE PRIOR TO FINAL |
| 06/03/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - LOOKED AT FORMS FOR VALLEY GUTTER AND SIDEWALKS |
| 05/14/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME |
| 05/08/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SITE WORK AT THIS TIME |
| 05/01/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME |
| 04/28/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) NO SIGNIFICANT SITE WORK AT THIS TIME
2) NO SIGNIFICANT STORM WATER COCERNS AT THIS TIME
3) ENSURE TRACKED SOIL IS SWEPT UP ROUTINELY |
| 04/25/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR WORKING ON BUILDING, MINIMAL SITE WORK AT THIS TIME
2) NO SIGNIFICANT STORM WATER CONCERNS |
| 04/18/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER OR SITE/GRADING CONCERNS AT THIS TIME |
| 03/18/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT SITE/GRADING CONCERNS AT THIS TIME |
| 03/17/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - CONTRACTOR WORKING ON BLDG PAD, NO SIGNIFICANT SITE/GRADING |
| 03/12/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
CONTRACTOR WORKING ON BLDG PAD AND UTILITIES |
| 03/11/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) SITE IS LESS THAN 1 ACRE, THEREFORE NO STORM WATER PERMIT IS REQUIRED.
2) CONTRACTOR INSTALLING UTILITIES AND WORKING ON BLDG PAD AT THIS TIME.
3) NO SIGNIFICANT SITE WORK AT THIS TIME
4) NO STORM WATER CONCERNS |
| 02/20/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO ACTIVITY ON SITE
CONTRACTOR ROUGH GRADED SITE, SOME SEDIMENT CONTROLS IN PLACE |