| 01/06/2014 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - 1) SITE IS LESS THAN 1 ACRE THEREFORE A STORM WATER PERMIT IS NOT REQUIRED. HOWEVER DISTURBED SOIL MUST BE KEPT ON SITE DURING CONSTRUCTION. TEMP SEDIMENT CONTROLS ARE RECOMENDED.
2) ENSURE PEDESTRIAN ACCESS SLOPES MEET ADA.
3) CALL FOR INSPECTION FOR RE-BAR LAYOUT IN NEW TRASH ENCLOSURE.