Inspection Status: Passed
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/07/2014 |
ENGR Engineering Final
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 09/16/2014 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO CHANGES |
| 08/27/2014 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) PART OF THE SITE HAS BEEN COMPLETED AND SEPARATED FROM REMAINING CONSTRUCTION.
2) FIANL APPROVAL WILL NOT BE GIVEN UNTIL THE SITE/GRADINMG IS COMPLETED PER THE APPROVED PLANS |
| 08/07/2014 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT CHANGES TO SITE/GRADING. ENSURE CONTRACTOR SEPERATES REMAINING CONSTRUCTION FROM OCCUPIED BLDG |
| 08/04/2014 |
ENGR Engineering Final
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) COMPLETE SITE/GRADING CALL FOR RE-INSPECTION
2) COMPLETE LANDSCAPING