Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 04/23/2014 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - SITE/GRADING COMPLETED PER THE APPROVED PLAN, AWATING A CERT LETTER FROM THE ENG OF RECORD |
| 03/31/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - CONTRACTOR COMPLETED PHASE I OF PROJECT, HOWEVER SITE/GRADING FOR ENTIRE PROJECT HAS NOT BEEN COMPLETED THERFOR PERMIT WILL REMAIN OPEN UNTIL WORK SHOWN ON APPROVED PLAN IS 100% COMPLETE |
| 02/07/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - NO INSPECTION CALLED IN FOR SITE/GRADING. PHASE I OF PROJECT APPEARS TO BE NEAR COMPLETION |
| 01/29/2014 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) NO INSPECTION CALLED IN. FOLLOW UP INSPECTION SHOWS NO CHANGES AND/OR CONCERNS WITH SITE/GRADING
2) CONTRCTOR NEARING END OF FIRST PHASE OF PROJECT
3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 11/07/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR IS INSTALLING 4-30" CULVERT PIPES ACCROSS THE ENTRANCE TO THE SITE NEAR 22ND ST.
2) ENSURE PIPE INSTALL IS PER ADOT STD DETAIL SHOWN ON APPROVED PLAN.
3) NO SIGNIFICANT STORM WATER CONCERNS |
| 11/01/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - CONTRCTOR SETTING GRADES AND PREPPING SOIL FOR CULVERT PIPE INSTALL |
| 07/18/2014 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 07/18/2014 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |
| 07/18/2014 |
ENGR Grading Final |
DROBERTS |
Approved |
Entered by DROBERT5 - |