Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
| Date |
Description |
Inspector |
Results |
Comments |
| 03/14/2014 |
SITE - Stormwater Follow-up
|
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 02/07/2014 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 01/29/2014 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) NO INSPECTION CALLED IN. FOLLOW UP INSPECTION SHOWS NO CHANGES AND/OR CONCERNS WITH SITE/GRADING
2) CONTRCTOR NEARING END OF FIRST PHASE OF PROJECT
3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 01/14/2014 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 12/30/2013 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 11/07/2013 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - 1) CONTRACTOR IS INSTALLING 4-30" CULVERT PIPES ACCROSS THE ENTRANCE TO THE SITE NEAR 22ND ST.
2) ENSURE PIPE INSTALL IS PER ADOT STD DETAIL SHOWN ON APPROVED PLAN.
3) NO SIGNIFICANT STORM WATER CONCERNS |
| 11/01/2013 |
SITE - Stormwater Follow-up
|
MRUSSO |
Continued |
Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
RECOMMEND INSTALL OF TEMP SEDIMENT CONTROLS AROUND STOCKPILE. |