Inspection Status: Passed
Inspection History: ENGR Grading Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/11/2013 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 03/11/2013 |
ENGR Grading Final |
MRUSSO |
Approved |
Entered by DROBERT5 - |
| 02/20/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - SITE HAS BEEN PREPPED FOR PAVING AND SUBGRADE IS BEING SET.
THE SUPEINTENDENT STATED THAT A THIRD PARTY QA/QC CONTRACTOR WAS NOT REQUIRED ON SITE TO TEST SOILS FOR COMPACTION/DENSITY.
SUPERINTENDENT STATED THAT PAVING WILL TAKE PLACE THIS WEEK.
NO STORM WATER CONCERNS AT THIS TIME |
| 01/25/2013 |
ENGR Grading Final |
MRUSSO |
Continued |
Entered by DROBERT5 - 1) FOLLOW UP INSPECTION, MET W/ SUPERINTENDENT
2) SEDIMENT CONTROLS INSTALLED AND ARE IN PLACE
3) CONTRACTOR WORKING ON RET/DET BASINS ALONG WEST SIDE
4) NO CHANGES AND/OR CONCERNS AT THIS TIME |