Permit: DP12-0213

Parcel: 99999999A

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP12-0213

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
11/13/2013 ENGR Grading Final RLEDONNE Approved Entered by ARUIZ1 -
11/13/2013 ENGR Grading Final RLEDONNE Approved Entered by ARUIZ1 -
11/13/2013 ENGR Grading Final RLEDONNE Approved Entered by ARUIZ1 -
10/31/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GC NOT ON SITE . TO GO OVER WORKFOR FINAL.
10/28/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVITY ON SITE.
10/10/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GOT WITH GC ABOUT CERT LETTER FOR ALL GRADING AND DRAINAGE.
10/09/2013 ENGR Grading Final eleibol1 Continued Entered by ELEIBOL1 - Report from Ken Perry at ES, who stated that his field trip found that trash enclosures were accepted for solid waste pick-up for Shops A2, B3, B4, & H. Ken reiterated that future projects will need 10 by10-ft clear inside bollards, a couple of feet of offset from front corner of trash enclosure where parking is to the side/front to avoid potential clipping of cars, no woven wire mesh should be accepted (gates need to be opaque, 40-ft approach should be straight & clear of curbs or other obstructions, enclosure area & approach area shall not be in a stormwater flow line and have minimum 2% grade for postive gradient for flows to flow away from enclosure.
09/09/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WALKED SITE WITH DAVE GOT WITH CONTRACTOR ABOUT INSTALLING BIKE PARKING . AND PROVIDE LETTER TASH ENCLOSURE.
09/05/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO CHANGE TO TRASH ENCLOSURE.
08/28/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GRADING CONTRACTOR STABILIZATED DISTURBED AREA.
08/27/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - FINAL GRADING FOR STABILZATION ON AREA OFF SITE.
08/06/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVTY OUT BUILDINGS.
08/01/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
07/16/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GOT WITH GC ABOUT PALS IN PARKING AREA AT PAD H.
07/02/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - FINAL GRADING WORK AROUND BUILDING. ON PAD A-2.
07/01/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - STRADED PAVING WORK ON PAD A-3.
06/10/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - ALL CATCH BASINS COMPLET.
06/07/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PAD H TRASH ENCLOURES 10 BY 10 .
06/06/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON CURBS . AND BACK FILLING.
05/29/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PAD B-3 WORKING ON STORM PIPING AND BASINS .
05/28/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - FORMING CATCH BASIN ON WEST SIDE OF SITE. AT PAD B-3.
05/23/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - BOTTOM OF CATCH BASIN ONLY.
05/22/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS ON PAGE G-4.
05/20/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PAD B-3 PER HIGH LIGHT ON PAGE G4FOR STROM DRAIN PIPING.
05/15/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - CURB WORK ON PAD H. NO TRACK OUT AT THIS TIME.
04/30/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - ADD CONTROLS AT CATCH BASINS . FOR A-2 PAD AND H PAD.
04/23/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PADS H& A-2 WORKING ON WATER MAINS ONLY AT THIS TIME.
04/08/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVITY ON PAD A-2 OR PAD H.
04/05/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GOT WITH GC ABOUT SWPPP INFO FOR PAD H .AND PROVIDE SWPPP CONTROLS AT NEW BASINS FOR PADS H & A-2.
04/01/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON CATCH BASIN ON NORTH EAST SIDE OF PAD H. WORKING ON STROMDRAIN MANHOLE AT PAD A-2.
03/29/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSPECTOIN FOR PAD A-2 PAGE G-3 PER HIGH LIGHT. BASIN INPECTION FOR PAD H PER HIGH LIGHT ON PAGE G-5.
03/28/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - THIS INSPECTION IS FOR SITE H INSPECTION PER HIGH LIGHT ON PAGE C-5.
03/13/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON SITE SEWER. NO TRACK OUT OR GRADING ACTIVITY.