Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 02/14/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN INSTALLED PER YOUR SWPPP; HOWEVER ADDITIONAL CONTROLS MAY BE NEEDED ALONG THE NORTH PERIMETER.
2) ENSURE STORM WATER MAINT SELF INSPECTIONS ARE PERFORMED PER YOUR SWPPP.
3) PROVIDE A SIGNED COPY OF YOUR NOI AND POST IT ON SITE.
4) INSTALL, MAINTAIN AND USE A CONCRETE/MATERIALS WASH OUT ON SITE
5) RE-ESTABLISH YOUR ROCK ENTRANCE/EXIT AS NEEDED.
SWEEP UP SOIL TRACKING OFF PUBLIC ROADWAYS ROUTINELY |