Permit: DP12-0206

Parcel: 14028008D


Addresses:

2085 E GANLEY RD


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP12-0206

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
08/02/2013 ENGR Grading Final RLEDONNE Approved Entered by RLEDONN1 -
08/02/2013 ENGR Grading Final RLEDONNE Approved Entered by RLEDONN1 -
07/12/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PRE GROUT FOR SOUTH WALL OK.
07/10/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSTALLED LAST OF REBAR FOR SOUTH WALL.
07/09/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSTALLING REBAR IN SOUTH WALL .INSTALLING WIRE FOR SHOT CRECTE ON SOUTH END OF SITE.
07/08/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - REBAR FOR SOUTH WALL INSPECTION.
06/20/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - FROMING HEAD WALL AT SOUTH END OF RCP PIPE.
06/18/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WALKED SITE WITH DAVE FOR HEAD WALL AND WALL ON NORTH SIDE OF SITE.
08/02/2013 ENGR Grading Final RLEDONNE Approved Entered by RLEDONN1 -
07/31/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSTALLING CHIP SEAL. IN LAY DOWN AREA.
07/30/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON FINAL GRADING FOR FOR CHIP SEAL.
07/24/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON PARKING AREA ON SOUTH SIDE OF SITE.
07/16/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GRADING WORK IN PARKING AREA ON SOUTH SIDE OF SITE .
07/01/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - REBAR INSTALLED FOR SOUTH SIDE WALL .
06/21/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - STILL WORKING ON HEAD WALL AND WALL ON NORTH END OF SITE.
06/19/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - FOOTER FOR WEST SIDE WALL.
06/17/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSPECTION PER HIGH LIGHTS ON PAGE 3 OF 27.
06/11/2013 ENGR Grading Final DROBERTS Continued Entered by DROBERT5 - LOOKED OVER THE OPEN CUT DRAINAGE CHANNEL ALONG THE SOUTH AND EAST SIDES OF THE SITE. THE CONTRACTOR HAS PLACED THE BEDDING MATERIAL FOR THE FUTURE PLACEMENT OF REINFORCED CONCRETE PIPE, THIS WORK WILL BEGIN TOMORROW.
06/13/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - INSTALLING RCP PER KEY NOTE #8 ON PAGE 6 OF 27.
06/05/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - PICKED UP PER-CON PACKET AND NOI FROM GC. STILL GRADING ON SITE.
05/13/2013 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GC NOT ON SITE ONLY NPPO WORK BEING DONE.
10/23/2013 ENGR Grading Final RLEDONNE Approved Entered by RLEDONN1 -