Inspection Status: Passed
Inspection History: SITE - Stormwater Follow-up
Permit Number - DP12-0053
Inspection Description - SITE - Stormwater Follow-up
Inspection Status - Passed
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/24/2014 | SITE - Stormwater Follow-up | MRUSSO | Approved | Entered by DROBERT5 - |
| 06/18/2014 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO CHANGES OR CONCERNS AT THIS TIME |
| 01/31/2014 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 01/23/2014 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SITE CHANGES OR CONCERNS. NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 01/07/2014 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - SITE NOT BUILT OUT, CONSTRUCTION OF RESIDENTIAL HOUING TAKING PLACE. NO CHANGES AND/OR SITE WORK AT THIS TIME. |
| 12/23/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 12/10/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - 1) CONTRACTORS BLDG HOUSES ON LOTS 2) GRADING PERMIT NOT FINALED 3) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 11/25/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 11/05/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER/SITE CONCERNS AT THIS TIME |
| 10/04/2013 | SITE - Stormwater Follow-up | MRUSSO | Approved | Entered by DROBERT5 - PERIMETER WALL IN PLACE, CURB AND ROADWAY INSTALLED. RET/DET BASINS COMPLETE. HOWEVER BLDG LOTS ARE STILL DIRT. |
| 08/14/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO ACTIVITY, NO STORM WATER CONCERNS AT THIS TIME |
| 07/12/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO ACTIVITY ON SITE ROADWAYS, CURB AND BLDG PADS ARE COMPLETED. CONTRACTOR HAS NOT STARTED ON HOLMES |
| 06/07/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - SMALL SUBDIVISION, NO CHANGES AND/OR CONCERNS AT THIS TIME |
| 05/03/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION SWEEP UP SOIL OFF ADJACENT ROADWAY CONTRACTOR WORKING ON BLDG PADS AND CUTTING ROADWAY |
| 04/10/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME |
| 03/20/2013 | SITE - Stormwater Follow-up | MRUSSO | Continued | Entered by DROBERT5 - NO SIGNIFICANT STORMWATER/SITE CONCERNS AT THIS TIME |