Inspection Status: Passed
Inspection History: PDSD Engineering Division Pre-Construction SITE
| Date |
Description |
Inspector |
Results |
Comments |
| 10/09/2013 |
PDSD Engineering Division Pre-Construction SITE |
MRUSSO |
Approved |
Entered by DROBERT5 - MET WITH SUPERINTENDENT, DISCUSSED SWPPP, REQUIREMENTS AND SITE/GRADING WORK.
1) USEEXISTING BIRMS FOR SEDIMENT CONTROLS AS MUCH AS POSSIBLE. IN AREAS WHERE BIRMS WILL BE REMOVED, INSTALL BMP'S UNTIL THE SITE IS STABILIZED.
2) INSTALL AND USE A STABILIZED CONSTR ENTRANCE
3) A COPY OF YOUR NOI HAS BEEN POSTED AT THE ENTRANCE TO THE SITE
4) INSTALL A CONCRETE/MATERIALS WASH OUT ON SITE WHEN APPLICABLE.
5) PERFORM AND DOCUMENT STORM WATER SELF INSPECTIONS PER YOUR PLAN.
6) SWEEP UP ANY TRACKED SOIL OF ADJACENT ROADWAYS AS NEEDED. |