Permit: DP12-0036

Parcel: 13409018G


Addresses:

8530 E BROADWAY BL


Inspection Status: Passed

Inspection History: SITE - Stormwater Follow-up

Permit Number - DP12-0036

Inspection Description - SITE - Stormwater Follow-up

Inspection Status - Passed

Date Description Inspector Results Comments
03/04/2013 SITE - Stormwater Follow-up MRUSSO Approved Entered by DROBERT5 -
02/21/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO CHANGES AND/OR CONCERNS AT THIS TIME
02/19/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
01/28/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR POURED CURB ALONG THE PRIVATE ROADWAY ENTRANCE. A TRANSITION WAS MADE BETWEEN THE EXISTING WEDGE CURB AND NEW VERTICLE CURB. 2) THE CONTRACTOR NEEDS TO CLEAN UP THE CONCRETE WASH OUT AND RE-INSTALL IT 3) CONTRACTOR4 NEEDS TO MAINTAIN INSTALLED SEDIEMNT CONTROLS UNTIL THE SITE IS PAVED
01/10/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) DRAINAGE CHANNEL CONSTRUCTED ALONG WEST SIDE 2) SWEEP UP SOIL AT ENTRANCE/EXIT TO SITE 3) CONTRACTOR WORKING ON MAIN ENTRANCE OFF OF BROADWAY. 4) CONTRACTOR WORKING ON REMOVING POWER POLE FROM SITE. 5) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME
01/10/2013 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) INSPECTED STORM PIPE BEING INSTALLED ALONG SOUTH SIDE OF SITE. 2) PIPE CONNECTED TO A BUBBLER BOX LOCATED IN THE RET/DET BASIN. OK TO COVER 3) REPAIR SILT FENCE AND REMOVE MATERIAL FROM ONTOP OF FENCE. 4) SWEEP UP TRACKED SOIL.
12/14/2012 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - RAINING, NO ACTIVITY SEDIMENT CONTROLS IN PLACE
12/12/2012 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME
12/05/2012 SITE - Stormwater Follow-up RUSSO Continued Entered by DROBERT5 - 1) WALKED SITE, INSPECTED RUN OF SRP ALONG FRONT OF SITE FROM RET BASIN TO FAR NORTH WEST CORNER WEIR. 2) REPAIR PERIMETER SEDIMENT CONTROLS AND DOCUMENT THE REPAIR. 3) CALL FOR RE-INSPECTION WHEN COMPLETED.
12/03/2012 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME
11/28/2012 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) INSPECTED STORM PIPE BEING INSTALLED ALONG SOUTH SIDE OF SITE. 2) PIPE CONNECTED TO A BUBBLER BOX LOCATED IN THE RET/DET BASIN. OK TO COVER 3) REPAIR SILT FENCE AND REMOVE MATERIAL FROM ONTOP OF FENCE. 4) SWEEP UP TRACKED SOIL.
11/16/2012 SITE - Stormwater Follow-up MRUSSO Continued Entered by DROBERT5 - 1) REPAIR/REPLACE SILT FENCE ALONG NW AND TNE NORTH SIDE OF SITE 2) SWEEP UP TRACKED SOIL OFFF ADJACENT ROADWAY ROUTINELY. 3) 63 LF OF 12" PVC SDR 35 WAS INSTALLED FROM BUBBLER BOX TO CANOPY LATERAL ( SLOPE @ 1% OR GREATER) - CLEAN OUT NOT IN YET. 4) NEED TO VERIFY BUBBLER BOX GRAVEL PACK IS 4' DEEP AND 1-3" ANGULAR ROCK. - OK 5) CALL FOR INSPECTION PRIOR TO COVER FOR ANY AND ALL STORM DRAIN LINE INSTALLATION - NEED TO VERIFY MATERIAL, SLOPE, DIMENTION, ETC.... 1 1/2 - 3" ROCK IN BUBBLER BOXES 64' OF 21'X15' SQUASHED CMP BASIN TO BASIN 71' OF 8" PVC @ BUBBLER SOUTH OF BLDG 130' OF 12" PVC FOR CANOPY LATERAL W/4" ROOF DRAIN LINES 150' OF 3" ROOF FROM BLDG