Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP12-0017

Parcel: 128010230


Addresses:

6100 E BROADWAY BL


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP12-0017

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
08/30/2013 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 -
08/27/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME
06/19/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO STORM WATER CONCERNS AT THIS TIME/ NO SITE WORK CONCERNS
05/20/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) LIMITED SITE WORK, CONTRACTOR WORKING ON THE BLDG
02/20/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) MET WITH SUPEINTENDENT AND DISCUSSED SITE WORK FOR PROJECT. 2) DURING THE REVIEW PROCESS IT WAS DETEMINED THAT THE SITE DISTURBANCE IS LESS THEN 1 ACRE; THEREFORE A STORM WATER PERMIT AND PLAN ARE NOT REQUIRED. 3) ENSURE THE ADJACENT ROADWAY IS SWEPT ROUTINELY DUE TO MINIMAL TRACKING OF SOIL FROM YOUR SITE 4) THE COT NEEDS CLARIFICATION FROM THE ENG OF RECORD FOR A 15,000 GAL RET/DET STORM WATER TANK TO BE INSTALLED. NO INLET DESCRIPTION, MATERIALS USED, SIZES, DIMENTIONS...ETC ARE SHOWN ON THE PLANS. SCOTT 214-460-6741
01/03/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 2) VERIFIED PROGRESS OF CONSTRUCTION ON BLDG. 3) NO SIGNIFICANT CHANGES AND/OR CONCERNS
12/13/2012 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO CONCERNS OR CHANGES AT THIS TIME
12/03/2012 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT CHANGES AN/OR CONCERNS AT THIS TIME
10/24/2012 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO CHANGES SINCE LAST INSPECTION. NO SIGNIFICANT STORM WATER CONCERNS
10/23/2012 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - CONTRACTOR IN SECOND PHASE OF PROJECT, NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME.
09/12/2012 ENGR Grading Final MRUSSO Continued Entered by MRUSSO1 - NO STORM WATER CONCERNS AT THIS TIME PAVING THIS WEEK
09/05/2012 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME
08/29/2012 ENGR Grading Final MRUSSO Continued Entered by MRUSSO1 - CONTRACTOR FORMING AROUND EXISTING CATCH BASIN, AND WORKING ON BLDG. SOME CURBING HAS BEEN POURED. NO STORM WATER CONCERNS AT THIS TIME
08/21/2012 ENGR Grading Final MRUSSO Continued Entered by MRUSSO1 - 1) ENSURE SIDEWALK RUN SLOPES ARE NO GREATER THAN 5%, AND CROSS SLOPES MUST BE NO GREATER THAN 2%. 2) NO STORM WATER CONCERNS AT THIS TIME. 3) RAIN > .5" LAST NIGHT, SEDIMENT CONTROLS IN PLACE, NI SIGNIFICANT CONCERNS. 4) NEED TO INSTALL CONCRETE VALLEY GUTTER AT NORTH SIDE OF LOT.
08/01/2012 ENGR Grading Final MRUSSO Continued Entered by MRUSSO1 - NO SIGNIFICANT CHANGES AND/OR CONCERNS AT THIS TIME. STORM WATER CONTROLS HAVE BEEN INSTALLED FOR THIS PHASE OF THE PROJECT CONTRACTOR WILL COMPLETE THE FIRST PHASE OF THE PROJECT PRIOR TO MOVING ON TO THE REMAINING SITE.