Permit: DP12-0013

Parcel: 13215001C


Addresses:

705 E AJO WY


Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP12-0013

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
10/18/2012 ENGR Grading Final RLEDONNE Approved Entered by RLEDONN1 -
09/20/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVITY ON SITE.
09/11/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVITY ON SITE.
08/23/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO ACTIVITY ON SITE.
08/20/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON STRIPING ON WEST SIDE OF BUILDING.
08/02/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON WEST SIDE DOCK AREA. GEN CONTRACTOR NOT ON SITE.
07/19/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GOT DAN LOOKING TO FINAL NEXT WEEK.
07/17/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO TRACK OUT
07/11/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON LANDSCAPING ON EAST SIDE OF BUILDING.
07/09/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WALKED SITE WITH MIKE.
07/03/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - CONTRACTOR CALLED FOR ON SITE MEETING AND WAS NOT ON SITE.
06/27/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON CURBING ON WEST SIDE OF BUILDING.
06/18/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON EAST SIDE OF BUILDING ON CURBING AND GRADING.
05/29/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - GRADING ON WEST SIDE OF BUILDING.
05/23/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON PHASE #2OF PARKING AREA.
05/18/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - REMOVING PAVEMENT TO START PHASE #2. NO CONCERNS AT THIS TIME.
05/15/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
05/09/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - EAST SIDE PARKING AREA PAVED AND STRIPED.
05/04/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON CRUBING ON WEST SIDE OF BUILDING.
05/03/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO CONCERNS AT THIS TIME.
04/13/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON CURBING ON EAST SIDE PARKING AREA.
04/11/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - WORKING ON GRADING ON EAST AND WEST OF BUILDING.
04/06/2012 ENGR Grading Final RLEDONNE Continued Entered by RLEDONN1 - NO TRACK OUT AT THIS TIME.