Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Permit: DP11-0022

Parcel: 13612001P

Inspection Status: Passed

Inspection History: ENGR Grading Final

Permit Number - DP11-0022

Inspection Description - ENGR Grading Final

Inspection Status - Passed

Date Description Inspector Results Comments
10/08/2013 ENGR Grading Final MRUSSO Approved Entered by DROBERT5 - PRIOR TO FINAL APPROVAL 1) COMPLETE SITE WORK PER THE APPROVED PLAN. 2) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD STATING THAT SITE/GRADING WAS CONSTRUCTED PER THE APPROVED PLAN 3) PROVIDE AN AS BUILT DRAWING 4) COMPLETE ALL LANDSCAPING PER PLAN 5) RESTORE ADJACENT WASH TO PRE-CONSTRUCTION CONDITION/HYROSEED AND REMOVAL OF DEBRIS 6) FILE A NOTICE OF TERMINATION (NOT) WITH ADEQ 7) PROVIDE APPROVAL FROM THE LANDSCAPE ARCH ON CHANGES MADE TO LANDSCAPE STABILIZATION
09/17/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) CONTRACTOR INSTALLING GROUTED RIP RAP ALONG THE SLOPE AT THE NORTH SIDE OF THE SITE. 2) CONTRACTOR PREPPING FOR PAVING
08/28/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - SOME EROSION CONTROL ALONG SIDE SLOPES STILL TO BE DONE. SITE STILL MUST BE PAVED NO OTHER CONCERNS OR CHANGES
07/23/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO CONCERNS AND/OR CHANGES AT THIS TIME
07/12/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) WORK ON BLDG, NO SIGNIFICANT SITE WORK BEING DONE 2) EROSION DAMAGE OF SLOPES, NEED REPAIRED 3) RE-ESTABLISH SEDIMENT CONTROLS AROUND ADJACENT WASH 4) ENSURE STORM WATER SELF INSPECTIONS ARE PERFORMED AND DOCUMENTED
06/27/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) WALKED PERIMETER OF SITE 2) ENSURE SEDIMENT CONTROLS ARE MAINTAINED THROUGHOUT CONSTRUCTION 3) ADJACENT WASH MUST BE REPAIRED BACK TO PRE-CONSTRUCTION CONDITION 4) CONTRACTOR IS GOING TO WORK ON FINAL STABILIZATION OF THE SLOPES ON SITE
06/11/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SITE WORK AT THIS TIME. PERIMETER WALL BEING INSTALLED ALONG THE SOUTH SIDE
05/01/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - NO SIGNIFICANT STORM WATER CONCERNS AT THIS TIME NO CHANGES TO THE GRADING PLAN UTILITY WORK BEING DONE, SOME SITE WORK
04/24/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - CONTRACTOR IS INSTALLING A SEWER LINE CROSSING THE WASH, ENSURE SEDIEMNT CONTROLS ARE IN PLACE DURING CONSTRUCTION. WASH MUST BE REPAIRED TO PRE-CONSTRUCTION CONDITION AFTER INSTALL
04/05/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 -
03/27/2013 ENGR Grading Final MRUSSO Continued Entered by DROBERT5 - 1) THE REGULATED WASH USED AS A CONSTRUCTION ACCESS POINT TO HAUL SOIL ON SITE MUST BE RESTORED TO PRE-CONSTRUCTION CONDITITON PRIOT TO FINAL APPROVAL 2) SEDIMENT CONTROLS ARE IN PLACE. NO OTHER SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 3) BLDG PAD IS BEING CONSTRUCTED