Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/04/2013 | ENGR Engineering Final | MRUSSO | Approved | Entered by DROBERT5 - |
10/30/2013 | ENGR Engineering Final | MRUSSO | Partial Approval | Entered by DROBERT5 - 1) CONTRACTOR HYDROSEEDED AREA ALONG WASH AND DISTURBED AREAS AROUND THE SITE. 2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENG OF RECORD 3) SUBMIT AN AS-BUILT DRAWING TO THE CITY OF TUCSON. 4) PROVIDE A LETTER FROM THE LANDSCAPE ARCHITECT APPROVING THE CHANGES MADE TO THE LANDSCAPE PLAN |
10/16/2013 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - 1) ENSURE ALL AREAS DISTURBED DURING CONSTRUCTION ARE STABILIZED USING HYDROSEEDING DESCRIBED IN THE APPROVED PLANS. 2) PROVIDE A CERTIFICATION STATEMENT FROM THE ENG OF RECORD 3) SUBMIT AN AS-BUILT DRAWING TO THE CITY OF TUCSON. 4) PROVIDE A LETTER FROM THE LANDSCAPE ARCHITECT APPROVING THE CHANGES MADE TO THE LANDSCAPE PLAN |
10/08/2013 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - PRIOR TO FINAL APPROVAL 1) COMPLETE SITE WORK PER THE APPROVED PLAN. 2) PROVIDE A CERT STATEMENT FROM THE ENG OF RECORD STATING THAT SITE/GRADING WAS CONSTRUCTED PER THE APPROVED PLAN 3) PROVIDE AN AS BUILT DRAWING 4) COMPLETE ALL LANDSCAPING PER PLAN 5) RESTORE ADJACENT WASH TO PRE-CONSTRUCTION CONDITION/HYROSEED AND REMOVAL OF DEBRIS 6) FILE A NOTICE OF TERMINATION (NOT) WITH ADEQ 7) PROVIDE APPROVAL FROM THE LANDSCAPE ARCH ON CHANGES MADE TO LANDSCAPE STABILIZATION |
03/27/2013 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - 1) THE REGULATED WASH USED AS A CONSTRUCTION ACCESS POINT TO HAUL SOIL ON SITE MUST BE RESTORED TO PRE-CONSTRUCTION CONDITITON PRIOT TO FINAL APPROVAL 2) SEDIMENT CONTROLS ARE IN PLACE. NO OTHER SIGNIFICANT STORM WATER CONCERNS AT THIS TIME 3) BLDG PAD IS BEING CONSTRUCTED |
03/19/2013 | ENGR Engineering Final | MRUSSO | Continued | Entered by DROBERT5 - 1) SEDIMENT CONTROLS HAVE BEEN ADDED TO THE AREA CROSSING THE 404 WASH. 2) CONTROLS NEED TO BE MAINTAINED AS LONG ACCES IS BEING USED IN THE WASH 3) WASH NEED TO BE RESTORED TO PRE-CONSTRUCTION STATE PRIOR TO FINAL APPROVAL 4) SEDIMENT CONTROLS NEED TO BE INSTALLED AROUND THE STOCK PILE UNTIL REMOVED. |