Case: T19DV07453
Case Details
Entered Date:
09/23/2019
Applicant:
BELVEDERE JO ANN & MICIELLI DEBRA M JT/RS
Description:
emergency
Completed Inspections
Case Status: COMPLIAN
Case Number: T19DV07453
Case Description: EMERGENCY
Total Completed Inspections - 2
| End Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/23/2019 | INSP - INITIAL CODE ENFORCMENT | LOPEZ | Approved | After inspection found that roof was 75% blown off, rafters were still intact only top layer was ripped off, water was getting into the ceiling wetting electrical, water heater was pulled up with the force of wind. I will be posting on safe to occupy electrical breakers turned off gas was pinned. ( PERMITS NEEDED FOR DAMAGED WATER HEATER, ROOF, INTERIOR CEILING WAS DAMAGE ALSO ) |
| 11/01/2019 | INSP - FOLLOW UP CODE ENFORCE | LOPEZ | Approved | PROPERTY STILL VACANT AND SECURED, PERMIT IN ISSUED STATUS AND WILL BE CLOSING CASE |
Completed Activity Special Conditions
Case Description - EMERGENCY
Case Number - T19DV07453
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 2
| Date | Name |
| 09/23/2019 | CONTACTED BY MAILING |
| 09/23/2019 | NOTICE OF VIOLATION ISSUED |