Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Case: T19DV00542
Case Details
Entered Date:
01/31/2019
Applicant:
BP SWAN INVESTORS LLC 55% & MAIZLISH COLLEGE PARTNERS GLS LLC 45%
Description:
FIRE AT COMMERCIAL BUILDING
Completed Inspections
Case Status: COMPLIAN
Case Number: T19DV00542
Case Description: EMERGENCY
Total Completed Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
01/31/2019 | INSP - INITIAL CODE ENFORCMENT | VALDEZ | Approved | EMERGENCY CALL OUT BY TFD: BUILDING 12 HAD FIRE DAMAGE TO A 15 X 15 COMPARTMENT, THERE IS DAMAGE TO CEILING METAL GRID AND DRYWALL, THE PARTITION WALL ALSO HAS WOOD STUDS WITH FIRE DAMAGE. THE INTERIOR STEEL DOORS AND FRAMES HAVE HEAT DAMAGE. THE FLOORING HAS DEBRIS AND WATER DAMAGE. THERE IS BARE AND DAMAGED WIRING AND ELECTRICAL DEVICES IN THIS AREA. THE OTHER ADJACENT COMPARTMENTS ALSO HAVE DRYWALL DAMAGE AND SEVERE SMOKE DAMAGE. THE BUILDING HAS EXTERIOR STEEL DOORS WERE PRIED OPEN AND HAVE DAMAGE. THIS PROPERTY DOES NOT HAVE POWER OR GAS OR WATER. THE BUILDING HAS MULTIPLE BROKEN OR MISSING WINDOWS WHICH WERE BOARDED PRIOR TO FIRE. THE REST OF THE BUILDING HAS HAD THE WIRING AND DEVICES CANNIBALIZED ALONG WITH MECHANICAL EQUIPMENT. THIS BUILDING WAS VACANT AND BROKEN INTO BY TRANSIENTS. OWNER WILL SECURE THE BUILDING. |
02/01/2019 | INSP - FOLLOW UP CODE ENFORCE | VALDEZ | Approved | ALL DOCUMENTS AND PHOTOSIN SIRE. CLOSE CASE |
Completed Activity Special Conditions
Case Description - EMERGENCY
Case Number - T19DV00542
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 4
Date | Name |
01/31/2019 | CONTACTED IN PERSON |
01/31/2019 | NOTICE AND ORDER ISSUED |
02/01/2019 | VIOLATION CLOSED |
01/31/2019 | 8-5 CITY COMM EMERGENCY |