Case: T17DV02240
Case Details
Entered Date:
05/31/2017
Applicant:
HSL 60 N ALVERNON LLC
Description:
main panel replaced and all new wiring put in without permits dry wall was put in and wiring is now covered up
Case Violations
Case Number: T17DV02240
Case Status: COMPLIAN
Case Description: WORK WITHOUT PERMITS-COMMERCL
Total Violations: 2
Violation Date | Code Statue |
---|---|
06/02/2017 | T.C. Ch. 16, Sec. 16-4. PERMITS REQUIRED. Unless otherwise exempt pursuant to section 301 of the Administrative Code, as adopted by reference per section 6-1 of this Code, or pursuant to any other ordinance or statute, no building, structure or building service equipment regulated by this chapter or by the technical codes adopted by the city shall be built, erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted or demolished unless a permit first has been obtained from the building official in the manner provided in the administrative and building codes adopted by the city. The purpose of a permit is to ensure that all construction is inspected by qualified City of Tucson personnel as directed by ordinance to verify compliance with city codes. Failure to obtain proper permit with inspections and approvals shall deem the construction to be unsafe. |
06/02/2017 | T.C. Ch. 16, Sec. 16-11(c) ELECTRICAL SYSTEM. (1) All dwellings and dwelling units shall be provided with electrical service. Electrical facilities connected to or in any building or structure are to be maintained hazard-free and in a state of good repair. The electrical system shall be free from such hazards as bare wiring; overloaded circuits or services; equipment not properly grounded; over-fused circuits; misuse of wiring, including the use of extension cords in lieu of permanent wiring; non-approved wiring; and wiring exposed to moisture or extreme heat. Broken, loose, frayed, inoperable, defective or missing portions of the electrical service, lines, switches, outlets, fixtures and fixture coverings shall be repaired or replaced. (2) All electrical equipment, wiring and appliances shall be installed and maintained in a safe manner and in accordance with all applicable laws. |
Outstanding Inspections
Case Number: T17DV02240
Case Status: COMPLIAN
Case Description: WORK WITHOUT PERMITS-COMMERCL
Total Outstanding Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
11/13/2017 | NPO(EL)-MAIN/PANEL/SUB/DISCONT | HOLLANDER | Item closed | |
11/13/2017 | NPO(EL)-WIRING/SWITCH/OUTLT/FX | HOLLANDER | Item closed |
Completed Inspections
Case Status: COMPLIAN
Case Number: T17DV02240
Case Description: WORK WITHOUT PERMITS-COMMERCL
Total Completed Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/01/2017 | INSP - INITIAL CODE ENFORCMENT | HOLLANDER | Approved | Visited the site and after touring the exterior of the property where it was seen that new wires were hanging from the ceiling. The owner came out and met with me. He took me inside and I showed him the new wires and explained that permits were needed and issued a NOV. The NOV request panel locations and load caluclations as well as circuits. At this time it was not determined if other new work was done. |
11/13/2017 | INSP - FOLLOW UP CODE ENFORCE | HOLLANDER | Approved | Permit #T17CM05943 has been secured, inspected and passed. At this time Code Enforcement does not have any further jurisdiction or authority |
Completed Activity Special Conditions
Case Description - WORK WITHOUT PERMITS-COMMERCL
Case Number - T17DV02240
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 5
Date | Name |
07/25/2017 | CONTACTED BY PHONE |
06/02/2017 | CONTACTED IN PERSON |
06/02/2017 | STOP WORK ORDER ISSUED |
06/02/2017 | NOTICE OF VIOLATION ISSUED |
11/13/2017 | VIOLATION CLOSED |