Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Case Details

Status:

COMPLIAN

Type:

FIRE AT COMMERCIAL BUILDING
Address:

Entered Date:

08/14/2012

Applicant:

PARK AVE SOUTH LLC

Description:

COMMERCIAL FIRE

Case Violations

Case Number: T12DV07073
Case Status: COMPLIAN
Case Description: FIRE AT COMMERCIAL BUILDING
Total Violations: 4
Violation Date Code Statue
08/14/2012 UDC, Sec. 10.3.5. VIOLATION OF A SITE PLAN Failure to comply with conditions placed on an approved site plan shall constitute a violation of the UDC.
08/14/2012 UDC, Sec. 10.2.3. COMPLIANCE REVIEW, EXISTING DEVELOPMENT Any land used or occupied; any site improvement, modification, or construction started; any existing use or structure expanded, reconstructed, changed, or otherwise altered; and any land divided into multiple parcels without certification of compliance with the provisions of the UDC through a zoning review process is considered a violation of the UDC. Enforcement of violations shall be in accordance with Section 10.4, Penalties and Remedies.
08/14/2012 T.C. Ch. 16, Sec. 16-4. PERMITS REQUIRED. Unless otherwise exempt pursuant to section 301 of the Administrative Code, as adopted by reference per section 6-1 of this Code, or pursuant to any other ordinance or statute, no building, structure or building service equipment regulated by this chapter or by the technical codes adopted by the city shall be built, erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted or demolished unless a permit first has been obtained from the building official in the manner provided in the administrative and building codes adopted by the city. The purpose of a permit is to ensure that all construction is inspected by qualified City of Tucson personnel as directed by ordinance to verify compliance with city codes. Failure to obtain proper permit with inspections and approvals shall deem the construction to be unsafe.
08/14/2012 T.C. Ch. 16, Sec. 16-14(c) BUILDINGS AND STRUCTURES CONSTITUTING A NUISANCE. All buildings and structures are to be maintained so as not to pose a threat to the health and safety of any person or persons. The condition of a building or structure that meets any or all of the following is a public nuisance, is a violation of this chapter, and subjects the building or structure to abatement as provided in Article VI of this chapter, including demolition as provided in section 16-65: (3) The building, structure or any portion thereof has been damaged by fire, earthquake, wind, flood or any other cause, to such an extent that the structural strength or stability thereof is materially less than it was before the damage and is less than the minimum requirements of the building code for new buildings of similar structure, purpose or location.

Outstanding Inspections

Case Number: T12DV07073
Case Status: COMPLIAN
Case Description: FIRE AT COMMERCIAL BUILDING
Total Outstanding Inspections - 2
End Date Description Inspector Results Comments
11/26/2012 LUC - VIOL OF SITE PLAN - COND WNAVARRO Follow-up inspection
11/26/2012 NPO - WORK WITHOUT PERMIT WNAVARRO Follow-up inspection

Completed Inspections

Case Status: COMPLIAN
Case Number: T12DV07073
Case Description: FIRE AT COMMERCIAL BUILDING
Total Completed Inspections - 2
End Date Description Inspector Results Comments
08/13/2012 INSP - INITIAL CODE ENFORCMENT WNAVARRO Approved Visited site inspected, found the commercial building demolished by fire, condemned unit, contacted owner and explained the damage and what was needed to secure the structure, they explained that they had no way to secure the building and just to have us secure, called biff baker fence and also bathcrest and had units secured, will follow up
11/26/2012 INSP - FOLLOW UP CODE ENFORCE WNAVARRO Approved Visited site, inspected and found that the building has been removed, will call owner.

Completed Activity Special Conditions

Case Description - FIRE AT COMMERCIAL BUILDING
Case Number - T12DV07073
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 10
Date Name
12/12/2012 CONTACTED BY PHONE
08/14/2012 CONTACTED IN PERSON
08/17/2012 CONTACTED BY MAILING
08/17/2012 NOTICE OF VIOLATION ISSUED
02/12/2013 VIOLATION CLOSED
02/22/2013 SEC LETTER OF BILLING FOR $??? SENT TO OWNERS
11/19/2013 SEC BILLING - PAID
08/17/2012 STRUCTURE SECURED BY ???
08/14/2012 RESEARCH
08/17/2012 CALLBACK

Documents

File Name Document Type  
None DOCUMENTS VIEW
None IMAGES VIEW