Case: T11DV03718
Case Details
Entered Date:
05/23/2011
Applicant:
MICHAEL S & CHANA WINOKUR CP/RS
Description:
UNIT D FOUNDATION CRACKING IN KITCHEN UNDER FLOORING / SINK HOLE IN FRONT OF PROPERTY
Case Violations
Case Number: T11DV03718
Case Status: COMPLIAN
Case Description: MULTIPLE TYPES
Total Violations: 2
| Violation Date | Code Statue |
|---|---|
| 07/18/2011 | T.C. Ch. 16, Sec. 16-11(f)(3) Every floor and floor support shall be maintained in a safe and structurally sound condition, and every existing floor covering shall be maintained in safe condition that is free of defect or deterioration that creates an unsafe or unsanitary condition. |
| 07/18/2011 | T.C. Ch. 16, Sec. 16-12(e) ACCESSORY STRUCTURES. All accessory structures, including but not limited to detached garages, fences and walls, must be structurally sound and free of disrepair. Examples of disrepair include missing slats, posts or blocks, or damage, deterioration or rot. Fences and walls cannot be constructed or covered with materials not designed or commonly used for that purpose, such as pallets and tarps. Fences and walls must be properly anchored so as not to be in danger of failure or collapse. |
Outstanding Inspections
Case Number: T11DV03718
Case Status: COMPLIAN
Case Description: MULTIPLE TYPES
Total Outstanding Inspections - 2
| End Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/14/2011 | NPO(DL)-DILAPIDATED STRUCTURE | DJOHNSTO | Item closed | |
| 09/14/2011 | NPO - INT. BUILDING MAINTENANC | DJOHNSTO | Item closed |
Completed Inspections
Case Status: COMPLIAN
Case Number: T11DV03718
Case Description: MULTIPLE TYPES
Total Completed Inspections - 2
| End Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 07/13/2011 | INSP - INITIAL CODE ENFORCMENT | DJOHNSTO | Approved | Met with the occupant. He showed me a large crack in the tile in the kitchen floor. Wood fence in the rear is also in disrepair and is leaning inward. Took photos for SIRE. Send 30 day notice of violation to the property owners. Schedule follow up inspection for 30 days. |
| 09/14/2011 | INSP - FOLLOW UP CODE ENFORCE | DJOHNSTO | Approved | All repaire are complete. Close case. |
Completed Activity Special Conditions
Case Description - MULTIPLE TYPES
Case Number - T11DV03718
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 4
| Date | Name |
| 06/02/2011 | CONTACTED BY PHONE |
| 07/22/2011 | CONTACTED BY MAILING |
| 07/22/2011 | NOTICE OF VIOLATION ISSUED |
| 09/15/2011 | VIOLATION CLOSED |