Case: T10DV03275
Case Details
Entered Date:
05/19/2010
Applicant:
DAVID ALAN CONNOR
Description:
wop and no cofo
Case Violations
Case Number: T10DV03275
Case Status: COMPLIAN
Case Description: MULTIPLE TYPES
Total Violations: 2
Violation Date | Code Statue |
---|---|
06/09/2010 | UDC, Sec. 10.2.3. COMPLIANCE REVIEW, EXISTING DEVELOPMENT Any land used or occupied; any site improvement, modification, or construction started; any existing use or structure expanded, reconstructed, changed, or otherwise altered; and any land divided into multiple parcels without certification of compliance with the provisions of the UDC through a zoning review process is considered a violation of the UDC. Enforcement of violations shall be in accordance with Section 10.4, Penalties and Remedies. |
06/09/2010 | T.C. Ch. 16, Sec. 16-4. PERMITS REQUIRED. Unless otherwise exempt pursuant to section 301 of the Administrative Code, as adopted by reference per section 6-1 of this Code, or pursuant to any other ordinance or statute, no building, structure or building service equipment regulated by this chapter or by the technical codes adopted by the city shall be built, erected, constructed, enlarged, altered, repaired, moved, improved, removed, converted or demolished unless a permit first has been obtained from the building official in the manner provided in the administrative and building codes adopted by the city. The purpose of a permit is to ensure that all construction is inspected by qualified City of Tucson personnel as directed by ordinance to verify compliance with city codes. Failure to obtain proper permit with inspections and approvals shall deem the construction to be unsafe. |
Outstanding Inspections
Case Number: T10DV03275
Case Status: COMPLIAN
Case Description: MULTIPLE TYPES
Total Outstanding Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
12/08/2010 | NPO - WORK WITHOUT PERMIT | JVALDEZ | Follow-up inspection | |
12/08/2010 | LUC-NO C OF O | JVALDEZ | Follow-up inspection |
Completed Inspections
Case Status: COMPLIAN
Case Number: T10DV03275
Case Description: MULTIPLE TYPES
Total Completed Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
06/02/2010 | INSP - INITIAL CODE ENFORCMENT | JVALDEZ | Approved | THREE STEEL BUILDING HAVE BEEN CONSTRUCTED TO INCLUDE UNDERGROUND ELECTRICAL SYSTEM WITHOUT APPROVALS FROM THE CITY OF TUCSON AND PERMITS |
12/08/2010 | INSP - FOLLOW UP CODE ENFORCE | JVALDEZ | Approved | SCHEDULED A 60 DAY FOLLOW UP INSPECTION |
Completed Activity Special Conditions
Case Description - MULTIPLE TYPES
Case Number - T10DV03275
Case Status: COMPLIAN
Total Completed Case Activity Conditions: 8
Date | Name |
06/09/2010 | CONTACTED BY PHONE |
05/20/2013 | CONTACTED IN PERSON |
06/10/2010 | CONTACTED BY MAILING |
07/02/2010 | CONTACTED BY EMAIL |
06/10/2010 | NOTICE OF VIOLATION ISSUED |
04/05/2017 | VIOLATION CLOSED |
04/23/2013 | REINSPECTION FEE - FIRST |
05/10/2011 | INFORMATION |