Case: CE-VIO0724-02941
Case Details
Status:
Citation
Type:
High Priority / RMIN / UNIT 10 : Leak in unit caused roof to cave in, sky can be seen from inside unit
Address:
Entered Date:
07/29/2024
Applicant:
N/A
Description:
Completed Inspections
Case Status: Citation
Case Number: CE-VIO0724-02941
Case Description: High Priority / RMIN / UNIT 10 : Leak in unit caused roof to cave in, sky can be seen from inside unit
Total Completed Inspections - 2
End Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
07/29/2024 | COT - ENFC - Code Enforcement - Initial | In Violation | Roof damaged by recent storm activity. Unit #10 is vacant. #14 is currently experiencing water coming in to the unit each time it rains. Shutting this unit down. Water is coming in around the windows and doors at the front end of each rental unit. Property Management has obtained a Roofing Contractor to repair the roof. Currently the roof is covered with tarp and boards. Roof should be completely repaired with in the next two weeks. Contractor is Esconda Contracting Co. out of Marana, AZ. Completed shut down paper work for unit # 14. Rental units #9, 3, 2, 10, 6, 8, 7, 5, 15 are occupied appear to be dried out. Rental units 9, 10, 11, 1 are vacant and currently being repaired. Property management has shut off electrical to the vacant units. Permits are required for the storm damage repair. Posted nov and shutdown paper work for Property Manager who stated he would be back in the area later this afternoon to ensure rental unit is secured and occupant is relocated to another location. | |
09/24/2024 | COT - ENFC - Code Enforcement - Follow Up | In Violation | Apartment complex still has tarp on the roof. No permits have been applied for. Issue citation |