Permits
Address: 2802 E BLACKLIDGE DR
Date - 11/24/2024 8:36 a.m.
Total Number Of Permits - (8)
Permit | Status | Apply Date | Expired Date | Unit | Type | Description |
---|---|---|---|---|---|---|
TR-UTL-1223-02999 | Issued | 12/05/2023 | 01/04/2024 | Right-of-Way (ROW) - Utility | wo#2703890 2802 e blacklidge dr 13-14-32 ne emg main rpr s/sd of lot in dirt alley 10LF/sc | |
T19CM01811 | Canceled | 03/13/2019 | N/A | Residential Building - One or Two Family | DETACHED WORKSHOP | |
TR-ROW-0224-00143 | Issued | 02/09/2024 | 11/23/2024 | Right-of-Way (ROW) | The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 -\ Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024 | |
TR-UTL-0224-00256 | Void | 02/07/2024 | N/A | Right-of-Way (ROW) - Utility | (Denied - RESUBMIT REQUEST UNDER - ROW -CIP/JOC permit type) - The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings | |
T11CM00168 | FINAL | 01/20/2011 | 07/25/2011 | COMBO | INSTALL:ROOF TOP A/C UNIT ELECTRIC CIRCUIT UNDER T11EL00066 | |
T11EL00066 | FINAL | 01/07/2011 | 08/09/2011 | ELECT | ELECTRIC:UPGRADE TO 200 AMP APA | |
T11ME00024 | VOID | 01/20/2011 | N/A | MECH | INSTALL:ROOF TOP A/C UNIT | |
T21RW01780 | FINAL | 04/15/2021 | 05/15/2021 | ROW | W/O# 21R0842 - REPAIR LEAKING 4" STEEL MAIN IN ASPHALT @ 6 LF WORK COMPLETED 3/31/21 - PERMIT ISSUED AFTER THE FACT |
Record Requests
Address: 2802 E BLACKLIDGE DR
Date - 11/24/2024 8:36 a.m.
Total Number Of Requests - (4)
Request Number | Status | Request Date | Completed Date | Type | Description |
---|---|---|---|---|---|
REQ-0524-03744 | Complete | 05/20/2024 | 05/21/2024 | Requests | Requesting Permit extension for 60days. ----- Securement of Right-of-Entry agreements has taken longer than anticipated. This has called delays in installing private plumbing connections to residents in the neighborhood. |
REQ-0724-04765 | Complete | 07/08/2024 | 07/24/2024 | Requests | The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 7/08/2024- Request for 60 day Extension for restorations as of 7/25/2024 |
REQ-0924-06079 | Approved | 09/10/2024 | 09/10/2024 | Requests | The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 5/21/2024 - Request for 60 day Extension as of 5/26/2024 - Update - 9/10/24 Request for another 30 day extension as of 9/22/2024 when permit is set to expire. |
REQ-1024-07237 | Approved | 10/23/2024 | 10/23/2024 | Requests | The scope of work includes furnishing and installing approximately 900 linear feet of 8-inch DIP and 5,000 linear feet of 6-inch PVC water mains, 170 feet of 6”DIP, gate valves, cut & cap with drain valve assembly, fire hydrants, back flow prevention devices, water meter relocations and service connections. Pavement replacement as indicated on the drawings Updated 5/17/2024 - Traffic Control plan updated to close both Southbound Lanes of Country Club between Flowing Wells and Glenn St. Updated - 10/23/2024 - Request for 30 day Extension as of 10/23/2024 |