Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.
Address Search: 2699 S PANTANO RD
Search
Parcel Attributes
| Parcel | 13615383A |
|---|---|
| Jurisdiction | Tucson, Pima County |
| Water Course | Street+culvert |
| City of Tucson Zoning | C-2 |
| Tucson Ward | Ward 4 |
| Major Street & Route | Gateway Route |
| Pima County Data | Assessor, Recorder, Treasurer, ... |
| Parcel Map | Map |
| Parcel Attributes Issue? | |
Annexations & Original City Zoning (OCZ)
Address: 2699 S PANTANO RD
Date - 12/17/2025 6:09 a.m.
Total Number Of Annexations & Original City Zoning (2)
Rezoning Cases
Date - 12/17/2025 6:09 a.m.
Total Number Of Rezone Cases - (2)
Permits
Address: 2699 S PANTANO RD
Date - 12/17/2025 6:09 a.m.
Total Number Of Permits - (20)
| Permit | Status | Apply Date | Expired Date | Unit | Type | Description |
|---|---|---|---|---|---|---|
| TR-UTL-1123-02923 | Complete | 11/15/2023 | 06/16/2024 | Right-of-Way (ROW) - Utility | Place aerial fiber over lash on E Golf Links Rd from S Marc Dr to S Pantano Rd. Place 4 hand holes over existing conduit stub ups on S Pantano Rd from E Golf Links Rd to E Escalante Rd. Pull fiber. This is part of the TEP Joint relocate project. Update 5/21/2024 - Request for 30 day extension as of 5/17/2024 | |
| TR-UTL-1124-02156 | Inspections | 11/14/2024 | 03/02/2025 | Right-of-Way (ROW) - Utility | WO T125595. TEP will be removing 8 poles (89,88,185,21, 20,18,213,17), in the ROW 3'x3' holes 12' deep with be removed and backfilled. Will impact sidewalk. Locations are starting on Escalante along the East side of Pantano to Golf Links. 1 of 3. | |
| TR-ROW-1123-01332 | Withdrawn | 11/07/2023 | N/A | Right-of-Way (ROW) | Place 4 hand holes over existing Conduit stubs, Place aerial and buried fiber in conduit associated with TEP joint relocates on S Pantano Rd from E Golf Links Rd to E Escalante Rd for Teleport Communications America, LLC . | |
| TR-UTL-0923-02543 | Complete | 09/20/2023 | 01/14/2024 | Right-of-Way (ROW) - Utility | 323020 Site 3 - Install Approximately 456 LF of 8" Cured in Place Pipe. The Cured in Place Pipe is a trench-less technology for sewer rehabilitation and does NOT require disturbance of the earth. EMC will Rehabilitate the bench on MH's 8372-16 and MH 8372-12 | |
| T22CM05082 | Issued | 07/06/2022 | 02/22/2023 | Commercial Building | THIS PROJECT WILL BE COMPRISED OF:CHANGES ON THE EXISTING MONOPALM:· POSITION 1- REMOVE (1) ANTENN | |
| TC-UTL-0425-00030 | Issued | 04/26/2025 | 06/15/2026 | Utilities Permit | AT&T equipment upgrade on existing Sooner wireless communication facility. AT&T is currently on Sooner Tower and would like to swap out its older Nokia equipment for upgraded Ericsson equipment to increase wireless reception in the area. The upgrade will not increase tower height, will not increase ground footprint or lease area, and will maintain current structure stealthing. Exact SOW is as follows: CHANGES ON THE EXISTING MONOPALM: · REMOVE (6) EXISTING ANTENNAS. · REMOVE ALL EXISTING NOKIA RADIOS. · REMOVE EXISTING TMAS · REMOVE EXISTING ANTENNA MOUNT · INSTALL NEW MSFAA PINCH RING · INSTALL NEW VFA6-HD ANTENNA MOUNT · INSTALL NEW 840-370966K ANTENNA ON P1 A/B/C · INSTALL NEW AIR6419 B77D+AIR6419 B77G STACKED ANTENNA ON P2 A/B/C · INSTALL NEW 840-370799K ANTENNA ON P3 A/B/C · INSTALL NEW 4490 B5/B12A & 4415 B30 RADIOS ON P1 A/B/C · INSTALL NEW 4478 B14 AND 4890 B25/B66 RADIOS ON P3 A/B/C · REUSE EXISTING DC AND FIBER TRUNKS. · INSTALL (1) NEW 24 PAIR FIBER · INSTALL (2) NEW 6AWG POWER TRUNK · INSTALL (1) NEW DC9-48-60-24-8C-EV (SQUID) CHANGES IN THE EXISTING AT&T EQUIPMENT ENCLOSURE AREA: · REMOVE ALL (E) NOKIA BBUS · INSTALL E// BBU'S (BBU INFORMATION TO BE FINALIZED PRIOR TO CONSTRUCTION) · INSTALL (1) SAU, (1) XMU, (2) 6651 & (1) 6610 IN NEW FLX42 PURCELL CABINET · INSTALL (1) NEW DC12-48-60-0-25E (OUTDOOR) | |
| T22CM01516 | Issued | 03/02/2022 | 11/15/2023 | Commercial Building | Modification to an Existing Monopalm by adding (3) antennas, (6) radio heads, (1) Raycap, (1) hybrid | |
| D97S-032 | CLOSED | 09/10/1998 | N/A | DPHIST | GARNER AUTOMOTIVE, L.L.C. | |
| P98AN00174 | ISSUED | 01/21/1998 | N/A | ADDRNEW | ||
| T08CM03769 | FINAL | 11/25/2008 | 03/15/2010 | COMBO | INSTALLATION OF ANTENNAS | |
| T11EX00361 | CLOSED | 07/19/2011 | 09/17/2011 | EXCAV | TRENCHING +/- TO PLACE TIME WARNER FACILITIES ALONG PANTANO RD TRENCH WILL BE FROM BASE OF POLE AT SW COR. OF PROPERTY TO PROJECT PROPERTY | |
| T12CM02131 | FINAL | 04/23/2012 | 09/17/2013 | COMBO | ANTENNA REPLACEMENT - FAN PALM COMMUNICATION TOWER | |
| T16CM01679 | FINAL | 03/04/2016 | 03/21/2017 | COMBO | CELL TOWER | |
| T16EX00867 | FINAL | 03/21/2016 | 06/13/2016 | EXCAV | ACCESS MANHOLE # 17327 AND BORE 240' OF CABLE AND REPLACE 1248 PED WITH A CHARLES PED. WORK ORDER # N.049217 | |
| T16TC00699 | FINAL | 03/21/2016 | N/A | BARRICAD | ACCESS MANHOLE # 17327 AND BORE 240' OF CABLE AND REPLACE 1248 PED WITH A CHARLES PED. WORK ORDER # N.049217 | |
| T19CM00362 | FINAL | 01/18/2019 | 04/25/2020 | COMBO | CELL TOWER ANTENNA | |
| T19FO00909 | FINAL | 10/22/2019 | 10/11/2022 | FIREOPER | GARNER AUTOMOTIVE REPAIR | |
| T97CM04188 | C OF O | 12/19/1997 | 12/20/1998 | COMBO | AUTOMOTIVE GARAGE | |
| T98BU00524 | FINAL | 03/02/1998 | 07/10/2007 | GRADING | GRADING:200CY CUT & 555CY FILL | |
| T98EX00592 | CLOSED | 05/19/1998 | 07/18/1998 | EXCAV | EXCAV:APRON:30 FT & 5LF FIRE LINE |
Plans
Address: 2699 S PANTANO RD
Date - 12/17/2025 6:09 a.m.
Total Number Of Plans - (2)
| Plan Number | Status | Application Date | Exp Date | Unit | Type | Description |
|---|---|---|---|---|---|---|
| T08PRE0052 | APPLIED | 05/01/2008 | N/A | NEIGHBORHOOD NOTIFICATION -- LABELS | Request for presubmittal meeting regarding a possible special exception to allow a wireless communication facility concealed within an artificial palm tree, 65 feet in height. | |
| T08SE00030 | APPROVED | 08/05/2008 | 10/16/2013 | Zoning Examiner Full Notice -- ZEFNP | The special exception request dated 8/01/08 is for a new wireless communication facility within a 400 sqft lease area consisting of a 69' high tower disguised as a palm tree and associated ground equipment. |
Record Requests
Address: 2699 S PANTANO RD
Date - 12/17/2025 6:09 a.m.
Total Number Of Requests - (6)
| Request Number | Status | Request Date | Completed Date | Type | Description |
|---|---|---|---|---|---|
| REQ-0323-01815 | Complete | 03/27/2023 | 04/12/2023 | Requests | I am requesting an extension for this permit due to a material issue that has now been corrected and materials are now in market to begin construction. |
| REQ-0324-02215 | Withdrawn | 03/19/2024 | N/A | Requests | Place 4 hand holes over existing Conduit stubs, Place aerial and buried fiber in conduit associated with TEP joint relocates on S Pantano Rd from E Golf Links Rd to E Escalante Rd for Teleport Communications America, LLC . |
| REQ-0524-03430 | Denied | 05/08/2024 | N/A | Requests | **DENIED - NO PRE-ACTIVITY MEETING SCHEDULED VIA THE DASHBOARD ** TEP requesting additional requirements as well as supply issues. Request 90-day extension. Place aerial fiber over lash on E Golf Links Rd from S Marc Dr to S Pantano Rd. Place 4 hand holes over existing conduit stub ups on S Pantano Rd from E Golf Links Rd to E Escalante Rd. Pull fiber. This is part of the TEP Joint relocate project. |
| REQ-0524-03799 | Complete | 05/21/2024 | 05/21/2024 | Requests | (Default 30 day Renewal Request) -- Place aerial fiber over lash on E Golf Links Rd from S Marc Dr to S Pantano Rd. Place 4 hand holes over existing conduit stub ups on S Pantano Rd from E Golf Links Rd to E Escalante Rd. Pull fiber. This is part of the TEP Joint relocate project. |
| REQ-1125-06811 | Approved | 11/24/2025 | 12/08/2025 | Requests | AT&T equipment upgrade on existing Sooner wireless communication facility. AT&T is currently on Sooner Tower and would like to swap out its older Nokia equipment for upgraded Ericsson equipment to increase wireless reception in the area. The upgrade will not increase tower height, will not increase ground footprint or lease area, and will maintain current structure stealthing. Exact SOW is as follows: CHANGES ON THE EXISTING MONOPALM: · REMOVE (6) EXISTING ANTENNAS. · REMOVE ALL EXISTING NOKIA RADIOS. · REMOVE EXISTING TMAS · REMOVE EXISTING ANTENNA MOUNT · INSTALL NEW MSFAA PINCH RING · INSTALL NEW VFA6-HD ANTENNA MOUNT · INSTALL NEW 840-370966K ANTENNA ON P1 A/B/C · INSTALL NEW AIR6419 B77D+AIR6419 B77G STACKED ANTENNA ON P2 A/B/C · INSTALL NEW 840-370799K ANTENNA ON P3 A/B/C · INSTALL NEW 4490 B5/B12A & 4415 B30 RADIOS ON P1 A/B/C · INSTALL NEW 4478 B14 AND 4890 B25/B66 RADIOS ON P3 A/B/C · REUSE EXISTING DC AND FIBER TRUNKS. · INSTALL (1) NEW 24 PAIR FIBER · INSTALL (2) NEW 6AWG POWER TRUNK · INSTALL (1) NEW DC9-48-60-24-8C-EV (SQUID) CHANGES IN THE EXISTING AT&T EQUIPMENT ENCLOSURE AREA: · REMOVE ALL (E) NOKIA BBUS · INSTALL E// BBU'S (BBU INFORMATION TO BE FINALIZED PRIOR TO CONSTRUCTION) · INSTALL (1) SAU, (1) XMU, (2) 6651 & (1) 6610 IN NEW FLX42 PURCELL CABINET · INSTALL (1) NEW DC12-48-60-0-25E (OUTDOOR) |
| REQ-1225-06912 | Denied | 12/02/2025 | 12/08/2025 | Requests | AT&T equipment upgrade on existing Sooner wireless communication facility. AT&T is currently on Sooner Tower and would like to swap out its older Nokia equipment for upgraded Ericsson equipment to increase wireless reception in the area. The upgrade will not increase tower height, will not increase ground footprint or lease area, and will maintain current structure stealthing. Exact SOW is as follows: CHANGES ON THE EXISTING MONOPALM: · REMOVE (6) EXISTING ANTENNAS. · REMOVE ALL EXISTING NOKIA RADIOS. · REMOVE EXISTING TMAS · REMOVE EXISTING ANTENNA MOUNT · INSTALL NEW MSFAA PINCH RING · INSTALL NEW VFA6-HD ANTENNA MOUNT · INSTALL NEW 840-370966K ANTENNA ON P1 A/B/C · INSTALL NEW AIR6419 B77D+AIR6419 B77G STACKED ANTENNA ON P2 A/B/C · INSTALL NEW 840-370799K ANTENNA ON P3 A/B/C · INSTALL NEW 4490 B5/B12A & 4415 B30 RADIOS ON P1 A/B/C · INSTALL NEW 4478 B14 AND 4890 B25/B66 RADIOS ON P3 A/B/C · REUSE EXISTING DC AND FIBER TRUNKS. · INSTALL (1) NEW 24 PAIR FIBER · INSTALL (2) NEW 6AWG POWER TRUNK · INSTALL (1) NEW DC9-48-60-24-8C-EV (SQUID) CHANGES IN THE EXISTING AT&T EQUIPMENT ENCLOSURE AREA: · REMOVE ALL (E) NOKIA BBUS · INSTALL E// BBU'S (BBU INFORMATION TO BE FINALIZED PRIOR TO CONSTRUCTION) · INSTALL (1) SAU, (1) XMU, (2) 6651 & (1) 6610 IN NEW FLX42 PURCELL CABINET · INSTALL (1) NEW DC12-48-60-0-25E (OUTDOOR) |