Parcel Attributes
Parcel137040280
JurisdictionTucson
City of Tucson ZoningR-2
Water Course

Washes

Tucson WardWard 5
Tucson Registered NeighborhoodSunnyside
Pima County Data Assessor, Recorder, Treasurer, ...
Parcel Map Map

Annexations & Original City Zoning (OCZ)

Address: 12 E NEBRASKA ST
Date - 11/15/2024 2:42 a.m.
Total Number Of Annexations & Original City Zoning (1)
Plan Description Annexation Ordinance Effective Date OCZ Ordinance
C9-60-39 West To Silverbell Road And South To San Xavier Indian Reservation 2014 2045

Permits

Address: 12 E NEBRASKA ST
Date - 11/15/2024 2:42 a.m.
Total Number Of Permits - (3)
Permit Status Apply Date Expired Date Unit Type Description
TR-ROW-1222-00169 Complete 12/19/2022 02/04/2023 Right-of-Way (ROW) Air-Vacuum Excavation of 42 Utility Potholes approximately 12"x12" in size for the design phase of Tucson Water Project CIP No W961 Rodeo Addition Main Replacement Phase 2
TC-RES-1023-08747 Complete 10/12/2023 12/29/2024 Residential Building - One or Two Family Installation of new Private water service line from the Meter to 10' outside of the house (house Connection) part of Rodeo addition phase 2 TW project. The water line will be a 1-inch pex, buried at 14 inches. 12awg tracer wire will be taped to the pex every ten ft. from the new meter to the tie-in point. The new 5/8 meter will have a 1-inch meter valve installed on the customer's side.
T18CM02460 FINAL 04/03/2018 11/11/2018 COMBO UPGRADE UP TO 200AMP

Record Requests

Address: 12 E NEBRASKA ST
Date - 11/15/2024 2:42 a.m.
Total Number Of Requests - (1)
Request Number Status Request Date Completed Date Type Description
REQ-0524-03616 Complete 05/14/2024 06/18/2024 Requests 90 DAYS EXTENTION REQUIRED AS PAVING WORK DID NOT ALLOW US TO BE ON JOB SITE Installation of new Private water service line from the Meter to 10' outside of the house (house Connection) part of Rodeo addition phase 2 TW project. The water line will be a 1-inch pex, buried at 14 inches. 12awg tracer wire will be taped to the pex every ten ft. from the new meter to the tie-in point. The new 5/8 meter will have a 1-inch meter valve installed on the customer's side.